Collection

EIA Submissions and Decisions – 2022

2022 Submissions and Decisions

Projects subject to an EIA process under the 2020 EIA Regulations are listed below. Further information on the individual projects EIA and the decision status can be accessed by selecting the relevant link below. The link for each project will only be made accessible on receipt of the public notice as set out in regulation 11(8).

Project Title Developer Year Submitted OPRED Ref Public Consultation Started Under Review/Determined
Murlach Development (redevelopment of Skua, part of the Marnock-Skua field) BP Exploration Operating Company Limited 2022 ES/2022/002 Yes Determined
Talbot Field Development Chrysaor Petroleum Company U.K. Limited 2022 D/4273/2021 Yes Determined
Victory Field Development Shell U.K. Limited (Formerly Corallian Energy Limited) 2022 ES/2022/003 Yes Determined
Affleck Re-development NEO Energy 2022 D/4272/2021 Yes Determined
Rosebank Field Development Equinor UK Limited 2022 ES/2022/001 Yes Determined
Teal West Development Anasuria Hibiscus UK Limited 2022 ES/2022/006 Yes Determined
Captain EOR Stage 2 Phase II Development Ithaca Energy (UK) Limited 2022 ES/2022/007 Yes Determined
Avalon Field Development Ping Petroleum UK PLC 2022 ES/2022/005 Yes Under Review

Updates to this page

Published 14 April 2022
Last updated 17 January 2024 + show all updates
  1. Update the project status EIA Submissions and Decisions table from “Under Review” to “Determined” - Victory Field Development

  2. Status of Captain EOR Stage 2 Phase II Development updated.

  3. Rosebank status changed to Determined

  4. Status of Murlach Development updated.

  5. Change of status of Affleck Redevelopment Environmental Statement from ‘Under Review’ to ‘Determined’

  6. Murlach ES name change

  7. ES/2022/003 - Operator updated to "Shell U.K. Limited (Formerly Corrallian Energy Limited)"

  8. Teal West ES noted as determined.

  9. Talbot Field Development ES – status updated to determined

  10. Avalon public notice period started

  11. Avalon Field Development added

  12. Teal West Public Notice Started

  13. Captain ES and associated documents added

  14. Update to include Teal West Development ES

  15. ES/2022/003 - Victory Field development - "Public consultation started" updated

  16. Public consultations for Rosebank Field Development changed from "No" to "Yes"

  17. Link removed to Rosebank ES

  18. new entry in EIA Submissions and Determinations – 2022 page: Rosebank Field Development ES/2022/001

  19. New Environmental Statement added

  20. update to include Victory Field Development ES

  21. Public consultation started changed to "Yes"

  22. D/4273/2021 added

  23. Adding the Murlach ES link

  24. Typo "Operation" -> "Operating". Public consultation started from "No" to "Yes".

  25. First published.