Consultation outcome

Network Rail periodic review 2018: draft determination

This consultation has concluded

Detail of outcome

On 31 October 2018, the Office of Rail and Road published its Periodic review 2018: final determination as an outcome of this consultation.


Original consultation

Summary

Seeks views on the draft determination for the 2018 periodic review of Network Rail's outputs for control period 6.

This consultation was held on another website.

This consultation ran from
to

Consultation description

The 2018 periodic review (PR18) is the process through which we determine what Network Rail should deliver in respect of its role in operating, maintaining and renewing its network in control period 6 (CP6) and how the funding available should be best used to support this. CP6 will run from 2019-2024.

Our draft determination sets out our proposed decisions on this, along with our approach for how we will regulate Network Rail’s delivery in CP6.

Updates to this page

Published 12 June 2018
Last updated 23 November 2018 + show all updates
  1. Outcome published.

  2. First published.

Sign up for emails or print this page