Consultation outcome

Buckinghamshire, Hertfordshire and East of Berkshire Public Review closure notice

Updated 25 November 2022

New procurement to extend coverage of gigabit-capable broadband across the Buckinghamshire, Hertfordshire and East of Berkshire regions.

1. Introduction

The government’s ambition is to deliver nationwide gigabit-capable broadband as soon as possible. We recognise that there is a need for government intervention in the parts of the country that are not commercially viable; this is why the government has committed £5 billion for the hardest to reach parts of the country, ensuring that all areas of the UK can benefit. This will be spent through a package of coordinated and mutually supportive interventions, collectively known as Project Gigabit.

We wish to work collaboratively with industry to maximise efficiency, minimise market distortion and achieve our objectives within a tight time frame. To do this, we first identified the areas that were not commercially viable through the Open Market Review (OMR) and Public Review (PR) stages. This allowed us to understand from suppliers if there were any current or planned investment over the next three years in broadband infrastructure (Next Generation Access broadband, ultrafast and gigabit-capable) in the identified geography. For this Lot, the identified geography lay within the Buckinghamshire, Hertfordshire and East of Berkshire regions.

The box below shows the order of processes, from OMR to procurement.

  1. OMR

  2. Pubic Review

  3. Determine intervention areas for procurement

  4. Procurement

Through these stages, BDUK classifies premises as eligible/ineligible for subsidy on the basis of their existing or planned qualifying broadband infrastructure. Details on the classification system of White, Grey, Black and Under Review and methodology can be found in section 3.2 BDUK Classifications and methodology for this PR.

Premises categorised as White by BDUK during OMRs and PRs (ie eligible for subsidy) are grouped into Intervention Areas (IAs). IAs list those premises that will be targeted for subsidy in any potential procurement to follow this PR. To be clear, not all eligible premises may have been targeted for subsidy. The finalised IA will be issued to the market at the Invitation to Tender (ITT) stage of procurement so that suppliers can bid for subsidy to support delivery to this IA.

Further information on the OMR/PR process and how we reach our conclusions can be found in the Subsidy Control Guidance document.

2. Outcome of the preceding Open Market Review

Preceding the current PR stage, BDUK conducted an OMR for Buckinghamshire, Hertfordshire and East of Berkshire (Lot 26) from 12 August 2021 to 13 September 2021. This OMR requested information from suppliers regarding current and planned broadband infrastructure within the next three years.

All meaningful responses to the OMR were considered and where necessary used to determine eligible premises. Suppliers who responded to the OMR were informed of the classifications applied to the existing and planned infrastructure relevant to their submission.

The key findings of the OMR are presented in the postcode-level map showing eligible premises identified through the OMR for Buckinghamshire, Hertfordshire and East of Berkshire, and a list of eligible postcodes can be found on our website.

3. Outcome of the Public Review

3.1 Background

The PR for Buckinghamshire, Hertfordshire and East of Berkshire (Lot 26) ran from 4 February 2022 to 4 March 2022. During the PR, BDUK invited stakeholders (including broadband infrastructure operators, internet service providers, the public, and businesses) to provide feedback regarding which areas were made up of eligible premises.

Furthermore, BDUK carried out market engagement to seek feedback from suppliers about the design of the IA and Lot design, the Procurement Type (A - Local supplier, B - Regional supplier or C - Cross-regional supplier) and also the capacity of the market to bid for a potential procurement.

The PR stage aimed to validate the outcome of the preceding OMR to ensure that it correctly represented the information provided by suppliers over the course of the OMR.

Suppliers who missed contributing to the preceding OMR, had no definitive plans and/or evidence base on which to substantiate claims at that earlier stage, or had subsequently updated their plans had a final opportunity to notify BDUK before final determinations were made on premises eligibility. All meaningful responses were carefully considered and where necessary utilised to determine eligible premises. BDUK also sought feedback from Buckinghamshire, Hertfordshire and East of Berkshire County Councils. The finalised postcode-level map showing eligible premises is shown in Annex A of this PR Closure Notice. See postcode-level map.

A finalised list of postcodes showing White, Grey, Black and Under Review PR outcome has been published. A list of eligible (White/Under Review) premises is available to suppliers upon request.

The proposed IA shown in Annex B has been submitted to BDUK’s National Competence Centre (NCC) and obtained approval to proceed. The finalised IA will be available to bidders at the forthcoming ITT stage.

Changes to Lot area

Please note, Lot areas are not fully aligned to Local Authority (LA) boundaries. Specific Lot boundaries (and IAs) may flex during the OMR, PR and Pre-Procurement Market Engagement (PPME) processes to enable an optimum procurement to be put to the market.

Since the PR closed on 4 March 2022, the following changes have been made to the proposed Lot Boundary Area. Please note, the PR outcomes provided below, and shown in Annex A, include these changes and so are consistent with the proposed Lot Boundary Area shown in this document.

To be clear, the changes made during the PR to the Lot Boundary Area are as follows:

  • Removal of parts of Hertfordshire from scope including the constituencies of Watford, St Albans, Stevenage, North East Hertfordshire, Wellwyn Gatfireld, Hertford and Stortford and Broxbourne
  • Expansion to include a small area of Oxfordshire in the constituency of Henley which was previously part of the Oxfordshire and West Berkshire Lot 13
  • Expansion to include most of Berkshire including the unitary authority of West Berkshire which was previously part of the Oxfordshire and West Berkshire Lot 13

The reason for these changes were largely due to limited market interest in a procurement across the eastern and southern parts of the county of Hertfordshire based on market feedback provided during the PPME exercise.

Please note, BDUK are expecting at least a 0.3% change to the proposed IA due to updated information. The finalised IA will be issued to the market at the ITT stage of procurement so that suppliers can submit a tender for targeting subsidy within Lot 26’s IA.

3.2 BDUK Classifications and methodology for this PR

During the PR, BDUK categorised premises as gigabit White, Grey, Black or Under Review.

Subsidy control classifications are set out below:

  • White - indicates premises with no gigabit network infrastructure and none is likely to be developed within 3 years[footnote 1]
  • Grey - indicates premises where a single qualifying gigabit infrastructure from a single supplier is available or is to be deployed within the coming 3 years[footnote 1]
  • Black - indicates premises with two or more qualifying gigabit infrastructures from different suppliers being available, or will be deployed within the coming 3 years[footnote 1]
  • Under Review - indicates premises where suppliers have reported current or planned commercial broadband coverage, but where claimed current gigabit coverage has not been verified, or, in respect of planned build, where evaluators are confident that gigabit infrastructure will be delivered, but some risks to delivery remain, or there are some gaps in evidence

BDUK will only provide subsidy to target premises that have been designated as White. Premises which have been designated as Under Review may be included within the Deferred Scope of a procurement. Where this is the case, a further review will be undertaken to confirm whether they are Grey or White before they are released for build.

In accordance with the OMR/PR processes, supplier data submitted during the OMR and PR has been mapped using a methodology that protects commercially sensitive supplier data. To reflect this sensitivity, we will only release White and Under Review UPRNs.

3.3 Summary of PR findings - premises eligibility

For presentational purposes only, postcode-level has been used to present the map showing eligible premises (NB we will only subsidise build to premises which have been designated as White - postcodes are not used to determine IAs for subsidy).

For this purpose, postcodes have been classified as follows:

  1. A postcode is White if any White premises are present.
  2. A postcode is Under Review if any Under Review premises are present.
  3. A postcode is Black if all premises in the postcode are classified Black.
  4. A postcode is Grey if all premises are Grey or a mixture of Grey and Black.

A postcode-level map summarising these premises classifications is provided in Annex A. Suppliers - please note that this map does not show which UPRNs have been determined as White and Under Review.

The outcome of the PR is summarised in terms of White, Grey, Black and Under Review postcodes and premises below:

Postcode Classification Number of Postcodes Number of Gigabit Black Premises Number of Gigabit Grey Premises Number of Gigabit Under Review Premises Number of Gigabit White Premises
White 18,888 12,507 103,861 44,682 140,713
Under Review 16,382 14,882 111,126 156,519 0
Grey 25,633 43,909 410,702 0 0
Black 4,410 75,284 0 0 0
Total 65,313 146,582 625,689 201,201 140,713

3.4 Forthcoming procurement

During the PR stage for Buckinghamshire, Hertfordshire and East of Berkshire (Lot 26), BDUK sought responses from the market and other stakeholders to validate the Annex A Subsidy Control map (showing Gigabit White, Grey, Black and Under Review determinations).

BDUK also carried out market engagement to seek feedback from suppliers about the design of the proposed IA and Lot, the Procurement Type (A - Local supplier, B - Regional supplier or C - Cross-regional supplier) and also the capacity of the market to bid for a potential procurement.

The total public funding investment has been based on the final number of premises requiring subsidy. BDUK will confirm a budget drawn from public funding for this area within the forthcoming tender documentation. Details of any restrictions on the use of public subsidy will be explained within the tender documentation.

Indicative funding allocated to this Lot is as follows:

Type B - (Total of 40,320 UPRNs) approximately £58,659,000 split as follows:

  • Initial Scope: 23,994 UPRNs approximately £40,335,000
  • Deferred Scope: 16,326 UPRNs approximately £18,324,000

The procurement type selected for Buckinghamshire, Hertfordshire and East of Berkshire (Lot 26), following engagement with the market and other stakeholders, is anticipated to be a Type B Regional supplier procurement. A premises level map detailing the proposed IA can be found in Annex B.

The Regional supplier contract includes two categories of intervention: Initial Scope, where the Regional supplier should build as quickly as possible; and Deferred Scope where we wait and see whether commercial plans or voucher projects translate to delivery, but could then build if not.

For premises that are included in the Deferred Scope of contract, we will seek a price from the Regional supplier, but will not authorise build unless and until they are re-classified as White. We will always either descope Under Review premises or defer build to them and we will always descope Grey or Black premises.

Buckinghamshire, Hertfordshire and East of Berkshire’s (Lot 26) forthcoming procurement will be carried out in accordance with the Public Contracts Regulations 2015 (PCR2015). BDUK procurement approaches are designed to address the scale of the individual procurements. Buckinghamshire, Hertfordshire and East of Berkshire’s (Lot 26) procurement will be conducted in a transparent and non-discriminatory manner.

The Authority, BDUK, reserves the right to amend or withdraw the procedure for the competitive sourcing process at any time. Any amendments will be done in line with the Procurement Regulations. Suppliers acknowledge and accept that by issuing this document (PR Closure Notice) BDUK shall not be bound to progress or conclude any related procurement activity.

Under no circumstances shall the Authority incur any liability in respect of the information contained in this Closure Notice or supporting documentation.

Timescales

Activity Date
Procurement start date (SQ Launch) November 2022
Estimated contract award date July to September 2023

See Project Gigabit procurement timelines for more information.

3.5 Summary of PR findings

Please note PR findings were for the whole area of Lot 26’s original area; Buckinghamshire, Hertfordshire and East of Berkshire.

  • There are 140,713 White premises (out of 1,114,185) where the market does not intend to build, indicating there is a strong commitment from active suppliers across the three counties to reach a large proportion of premises in the Lot.

  • The IA was designed to address areas outside of where we expect the commercial sector to build to, prioritising footprints where there is an appetite for BDUK to go further, faster.

  • We contacted all known national and local suppliers to ask them to respond to the OMR and PR. This included working closely with Buckinghamshire Council, Hertfordshire County Council and the unitary authorities of Berkshire to ensure active and prospective suppliers were aware of the OMR and PR and could feed in their responses.

4. Conclusion

A key output for the OMR/PR for Buckinghamshire, Hertfordshire and East of Berkshire.(Lot 26) is the map showing premises that are eligible for subsidy.

From this map, BDUK developed the IA which was proposed to the market during the PPME phase. Annex B sets out the draft IA map at UPRN level.

This identifies the areas where premises are eligible for subsidy. A full list of White and Under Review UPRNs is available on request to suppliers via ukgigabit@BDUK.Zendesk.com.

5. Annex A – Map indicating locations of eligible premises

The postcode level map below indicates areas where those premises eligible for subsidy are located ie White areas. These eligible premises may be included within the IA.

Black, Grey and Blue (Under Review) areas indicate where those premises ineligible for Subsidy are located.

Buckinghamshire, Hertfordshire and East of Berkshire (Lot 26) level map (showing subsidy control classifications at a postcode level)

Buckinghamshire, Hertfordshire and east ofd Berkshire Public Review outcome postcode map

6. Annex B – Map of Proposed Intervention Area

The map below highlights the IA that was approved following completion of the PPME exercise.

Buckinghamshire, Hertfordshire and east of Berkshire intervention area map

Please see section 3 above for information on BDUK’s findings, contextualising how eligible premises were included in the proposed IA.

The above premises level map indicates eligible premises from the proposed Type B IA.

Those premises which are highlighted in orange (23,994 premises) are referred to as the ‘Initial Scope’ premises that will be targeted for subsidy.

Those premises which are highlighted in blue (16,326 premises) are referred to as the ‘Deferred Scope’ premises, which will not be targeted for subsidy unless they have been determined to be eligible (White) as part of BDUK’s monitoring process.

This map is accompanied by a list of UPRNs that fall within the IA, clearly demarcating which premises are within ‘Initial’ or ‘Deferred Scope’ which suppliers can request via ukgigabit@BDUK.Zendesk.com.

The Lot boundary for this Regional Supplier Contract has changed through the pre-procurement process as a result of feedback received from the market. BDUK went to market at the Soft Market Testing stage with different options. The market showed interest mainly focused in the Buckinghamshire area, and less so in Eastern Hertfordshire. As such, the boundaries were changed to reflect this, as referenced in Section 3.1 above.

Additionally, after the PPME exercise concluded, the IA was adjusted to incorporate the latest Epoch data, to include LB feedback on caravan data removing a few and to account for changes by Ordnance Survey on the way they showed New Builds. The boundary captures the entirety of Buckinghamshire Council’s area, parts of Hertfordshire County Council’s north east constituencies, and a significant area into all six of Berkshire’s unitary authorities. Additionally the revised Lot 26 boundary area includes a number of premises in the adjacent LAs; mainly Oxfordshire, with some UPRNs in Surrey and Bedfordshire.

  1. There may be occasions where credible plans extend beyond a 3-year period, in that case, these may be taken into account.  2 3