Energy investigation timetable published
The CMA has published a timetable setting out the timescales for the different stages of the energy market investigation.
Energy administrative timetable
Phase 2 | Action |
---|---|
26 June 2014 | Reference made by Ofgem |
July–September 2014 | Initial information requests; initial submissions from main and third parties; publication of initial issues statement |
September 2014 | Site visits, issue questionnaires |
October 2014 | Hearings with third parties |
January/February 2015 | Publication of relevant working papers and annotated issues statement |
February/March 2015 | Main party hearings |
March 2015 | Deadline for all parties’ responses/submissions required before provisional findings |
May–June 2015 | Notify provisional findings and possible remedies (if required) |
November–December 2015 | Publish final report |
25 December 2015 | Statutory deadline |
All information relating to the investigation will be available on the energy market case page.