MOD publishes equipment plan update and welcomes independent report
The third annual update on the Defence Equipment Plan has been published.
The Ministry of Defence has published its third annual update on its Defence Equipment Plan after an independent audit found the cost of the department’s 13 biggest equipment programmes fell by £247m last year.
The annual update to Parliament sets out the department’s spending plans over the next decade, including the intention to spend around £166bn on new equipment and support as part of a stable base for the Strategic Defence and Security Review (SDSR).
Today the National Audit Office (NAO) published its assessment of the affordability of both the plan and the MOD’s Major Projects Report – a review of a sample of key programmes – and found a strong cost and timely delivery performance. The NAO found that the Equipment Plan is more stable than last year and is set to remain affordable for the rest of the parliament under current conditions.
Across the sample of MOD projects that are included in the Major Projects Report this year, excluding the new decision to accommodate the production of an additional reactor core for HMS Vanguard, this was the best time performance since at least 2001.
Philip Dunne, Minister for Defence Procurement, said:
I welcome the NAO’s recognition of our progress in improving defence procurement. Along with our commitment to increase the defence budget and to meet the NATO target of spending 2% of GDP on Defence, we are ensuring our armed forces have the equipment they need at the best value for the taxpayer.
This is the third consecutive year of improving performance. The 2009 NAO report we inherited recorded £1.2bn in year overspend and 93 months in-year project overruns. By contrast, today’s report for 2014/15 shows an in-year cost reduction of £247m and underlying delivery eight months over forecast - a remarkable turnaround by any standards.
This latest Equipment Plan sets out our plan to spend £166bn on new kit and support for the Armed Forces over the next decade, including our new aircraft carriers and hunter killer submarines.
Equipment Plan
- The MOD plans to spend around £166bn on new equipment and equipment support over the next 10 years.
- We continue to hold a substantial contingency of £4.3bn over the period and further funding within the Equipment Plan of £7.3bn for capability investment but not yet committed to specific programmes.
Major Projects Report
- Of the 13 projects within the MPR sample of 17 projects that have passed the main investment decision point, we are expected to deliver 99% of requirements, maintaining the increase from last year.
- The forecast cost of the projects has reduced by £247m and only a small number of projects had a time delay totalling a small increase of eight months when the 52 months for the re-fuelling of HMS Vanguard is excluded.