Planned roadworks in the North West: summary for Monday 27 to Sunday 5 March 2017
Summary of planned new and ongoing road improvements over the coming week.
The following summary of planned new and ongoing road improvements over the coming week is correct as of Friday 24 February and could be subject to change due to weather conditions or unforeseen circumstances.
All our improvement work is carried out with the aim of causing as little disruption as possible. Drivers looking for roadworks information (such as overnight carriageway closures) for individual schemes should now visit Traffic England. Some of our larger schemes have project pages giving other information. These can now be accessed from a dedicated regional page.
M53 junction 1 to junction 2 (Wallasey to Upton)
Work to upgrade the safety barrier in the central reservation between junctions 1 and 2 on the M53 started on Monday 6 February. Lane closures will be in place overnight, with some full carriageway closures later in the project. The scheme is expected to take around a month to complete.
M53 junction 9 to junction 10
Overnight, 10pm to 5am, Monday to Friday work to renew the safety barrier in the central reservation started on Monday 20 February for 5 weeks. This work will require overnight carriageway closures with clearly signed diversion in place.
M56 junction 10 to junction 11 (Stretton to Preston Brook)
Work to upgrade the safety barrier and paint new road markings on the M56 near Warrington started on Monday 30 January. Lane closures will be in place overnight between 8pm and 5am, Monday to Friday. The project is due to be completed by the end of March.
M6 junction 16 to junction 19 (Cheshire smart motorway)
Work is underway to upgrade the M6 to a smart motorway between Crewe and Knutsford, converting the hard shoulder to an extra lane and introducing new variable speed limits. Narrow lanes and a temporary 50mph speed limit are in place for the safety of drivers and workers.
M6 junction 19 (Knutsford) roundabout resurfacing
A £75,000 project to resurface the junction roundabout will be delivered overnight during week nights over the next week. The work started on Monday night 20 February with nightly overnight closures of the roundabout between 10pm and 5am.
M6 Junction 21 and junction 21a (cycle improvements with A574 Birchwood Way)
We’re improving pedestrian and cyclist access across the M6 with improvements to the existing overbridge and along the bridge’s links with the A574 Birchwood Way. The project will also improve the bridge parapet. Works started Friday 17 February for 2 weeks.
Cycleway improvement work is taking place between 9.30am and 3.30pm Monday to Friday, requiring a 24 hour closure of the footway along the southern side of the A574 Birchwood Way with a localised pedestrian diversion route. A lane closure will also be required on the A574 Birchwood Way westbound carriageway between the same hours.
Bridge improvement works will follow between 10pm and 4am, Monday to Friday. The M6 between junction 21 and junction 21a will be closed overnight Friday 3 March (both northbound only) and Wednesday and Thursday 1 and 2 March (all southbound). Clearly-signed diversions will be in place.
M6 junction 21a and /M62 junction 10 (Croft Interchange)
Construction work on a major project to tackle congestion and improve the flow of traffic between the M6 and M62 at Croft Interchange has now started. While the work is taking place, a 50 mph speed limit, backed by average speed cameras, will be in place along main carriageways of both the M6 and M62 and interchange link roads. Some overnight slip road closures will also take place.
M6 junction 26 to junction 27 (Orrell to Wigan)
We’re renewing the boundary fence and carrying out drainage repairs in the verge alongside the northbound M6 between Junctions 26 and junction 27 in a 2 week project that starts on Monday (20 February). The work is taking place between 8am and 5pm, Monday to Friday.
M6 junction 33 to junction 32 (Lancaster to M55 interchange)
Resurfacing work on the southbound carriageway started on Monday 6 February. 2 lanes will remain open during the day and 1 lane will remain open overnight. The scheme is due to be completed by early March.
M6 junction 33 to 34 Lancaster
Lancashire County Council’s new link road between junction 34 of the M6 and Heysham has now opened but finishing work will require lane and hard shoulder closures along the M6 through junction 34 to continue for the time being.
The following closures will take place:
- Northbound from junction 33 to 34 Thursday 2 March 2017 from 10pm to 6am.
- Southbound from junction 35 to 34 Friday 3 March 2017 from 10pm to 6am.
M6 junction 39 to junction 38, north of Tebay Services
Resurfacing is taking place north of Tebay Services with 1 lane closed during the day and 2 lanes closed overnight on the southbound carriageway. The work is due to be completed by March and a temporary 50mph speed limit in place. Tebay services entry slip Southbound road will be closed on the 28 Feb for 1 night 10pm to 6am.
M60 junction 8 to M62 junction 20 (Sale to Rochdale)
A major smart motorway scheme is taking place to cut congestion and improve journey times on parts of the M60 and the M62 in Greater Manchester. The scheme involves overnight slip road and carriageway closures, with narrow lanes and a temporary 50mph speed limit in place for the safety of drivers and road workers.
M66 junction 1 to junction 4 (Ramsbottom to Simister Island)
Resurfacing work is continuing and 4 nights of closures of the southbound carriageway between junction 1 and junction 2 are scheduled to take place before Friday (24 February) between 9pm and 5am – with clearly signed diversions in place. The scheme is due to be completed by March.
A5103 Princess Parkway
Drainage repairs along the northbound exit slip road from the A5103 onto the M60 will start on Monday (20 February) with one lane of the slip road closed and re-positioning of the bus stop. Work will take place in several phases between 8am and 6pm and midnight and 5am.
A556 Knutsford to Bowdon
Construction work to provide a £192 million dual carriageway linking junction 19 of the M6 at Knutsford and junction 7 of the M56 at Bowdon, has entered its final phase. It is due to open on 6 March. On the existing A556, another full 56 hour weekend closure will run from 9pm next Friday night (3 March) and 5am on the following Monday morning (6 March).
Other work relating to the scheme:
Monday to Friday commencing 27 February:
- A556 northbound will be closed from Mere to Bowdon roundabout overnight (9pm to 5am)
- A556 southbound will be closed from Bowdon roundabout to Bucklow Hill overnight (9pm to 5am) as above
- M56 junction 7 eastbound and westbound exit slip roads will be closed
- M56 junction 8 will be closed. Junction 7 eastbound access slip will be closed
- A56 Lymm Road to Dunham Road will be controlled by traffic signals allowing access from Lymm to Altrincham and vice versa over the same periods as above
A585 West Drive to Fleetwood Cycleway
Work is taking place on a new shared footpath and cycleway between West Drive and Fleetwood. Narrow lanes and a temporary 30mph speed limit are being used along the route to help provide a safe space for workers constructing the new shared paths. Work will take place between 7am and 7pm each day with occasional overnight work. The project is due to be completed by the end of March.
A590 Lindal in Furness
Work is being carried out to tackle flooding between Pennington Lane and Bank End Cottages. 24hr temporary traffic lights are now in place until late March.
A595 Egremont
Repairs are taking place to the safety barriers adjacent to Wyndham Place on the A595 and are due to be completed by the end of February. A contraflow system is in place on the southern approach to the Main Street/East Road roundabout.
A66 Bassenthwaite Lake
A contraflow system is in place while work is carried out on the embankment in the central reservation next to Bass Lake. The scheme is due to be completed in the spring.
A66 Thornthwaite (Osprey Site)
Flood resilience work is continuing. Full overnight – 8pm to 6am - closures of the carriageway nightly until the end of March started on Monday 6 February. Clearly-signed diversions are in place. During the day, Temporary traffic lights are in place along with a 40mph speed limit.
A66 Marron Bridge
Maintenance is underway on Marron Bridge, between Broughton Cross and Bridgefoot. Nightly overnight – 9pm to 5am - closures, with a clearly-signed diversion are in place. Due to the temporary bridging plates, a 30mph speed limit backed by speed cameras is required during the day. The project is due to be completed by March.
A66 Brough
Resurfacing and drainage work is taking place on the eastbound carriageway at Brough. Overnight lane closures will be in place, between 8pm and 6am, with traffic led through the roadworks by a contractor’s vehicle. There will also be some lane closures in place during the day.
General enquiries
Members of the public should contact the Highways England customer contact centre on 0300 123 5000.
Media enquiries
Journalists should contact the Highways England press office on 0844 693 1448 and use the menu to speak to the most appropriate press officer.