Screening decision to upgrade 160m of existing overhead line by adding a third wire to an existing 2 wire. Adding a new pole mounted transformer, with an additional pole being installed 6ft from the existing transformer pole to support the weight of the new transformer.

Applies to England

Documents

Details

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

4 November 2024

Location

Somerset

Section 37 consent to install or keep installed an electric line.

Updates to this page

Published 4 November 2024