Abigail Field Development - Ithaca Energy (UK) Ltd - 2021 - D/4263/2021 - Determined
Key Dates
- Date Environmental Statement received by the department - 02/07/2021
- Public notice commencement date - 22/07/2021
- Public notice closing date - 25/08/2021
- Further information public notice commencement date - Not Applicable
- Further information public notice closing date - Not Applicable
Environmental Statement & associated documents
- Summary of the Project - Received Date 02/07/2021
- Environmental Statement - Received Date 02/07/2021
- Public Notice - Received Date 26/07/2021
Further Information
- Secretary of State request for provision of further information - Issued Date 06/10/2021
- Developer response to Secretary of State request for provision of further information - Received Date 28/10/2021
- Further information public notice - Not Applicable
Decision made by the Secretary of State
- Secretary of State notice under regulation 16(1) - 19/01/2022
- Secretary of State decision to agree to or refuse to agree to the OGA granting of consent - Letter to the developer - 20/01/2022
- Secretary of State decision to agree to or refuse to agree to the OGA granting of consent - 07/01/2022
Updates to this page
Last updated 20 January 2022 + show all updates
-
Update to status of Environmental Statement in details section and updates to 'Decision made by the Secretary of State' section of 'Key Dates' and addition of associated documents
-
Addition of Request for Further information and date response to same received
-