Decision

Affleck Re-development

Project summary

Documents

Summary of Project

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email OPRED@energysecurity.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Environmental Statement

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email OPRED@energysecurity.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Public Notice

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email OPRED@energysecurity.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Public Notice- The Courier

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email OPRED@energysecurity.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Public Notice – the Northumberland Gazette

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email OPRED@energysecurity.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Public Notice – the Daily Telegraph

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email OPRED@energysecurity.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Regulation 12(1) Notice for Further Information Request

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email OPRED@energysecurity.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Regulation 12(1) Notice for Further Information Request (2)

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email OPRED@energysecurity.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Secretary of State notice under regulation 16(1)

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email OPRED@energysecurity.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Secretary of State decision to agree to or refuse to agree to the OGA granting of consent - Letter to the developer

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email OPRED@energysecurity.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Secretary of State decision to agree to or refuse to agree to the OGA granting of consent

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email OPRED@energysecurity.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Details

Affleck Re-development - NEO Energy- 2022 - D/4272/2021 (Determined)

Key Dates

  • Date Environmental Statement received by the department - 27/07/2022
  • Public notice commencement date - 25/08/2022
  • Public notice closing date - 26/09/2022
  • Further information public notice commencement date -
  • Further information public notice closing date -

Environmental Statement & associated documents

  • Summary of the Project – Received Date 27/07/2022
  • Environmental Statement – Received Date 27/07/2022
  • Public Notice – Received Date 25/08/2022

Further Information

  • Secretary of State request for provision of further information – 31/01/2023 & 17/05/2023
  • Developer response to Secretary of State request for provision of further information – 06/04/2023
  • Further information public notice –

Decision made by the Secretary of State

  • Secretary of State notice under regulation 16(1) – 28/08/2023
  • Secretary of State decision to agree to or refuse to agree to the OGA granting of consent - Letter to the developer – 23/08/2023
  • Secretary of State decision to agree to or refuse to agree to the OGA granting of consent – 22/08/2023

Updates to this page

Published 3 August 2022
Last updated 13 October 2023 + show all updates
  1. Telephone number was incorrectly redacted in Regulation 16(1) Notice. The only change to the Regulation 16(1) Notice was to insert telephone number.

  2. Change of status of Affleck Redevelopment Environmental Statement from ‘Under Review’ to ‘Determined’

  3. Publication of documents related to decision and dates for the decision made by the Secretary of Sate for the Affleck Redevelopment Environmental Impact Assessment

  4. Regulation 12(1) letter uploaded and date added under Details

  5. Addition of date of Developer response to Secretary of State request for provision of further information

  6. Addition of request for provision of further information letter

  7. Public Notice added

  8. First published.