Aller Court Solar Park, replace tower and overhead lines: screening decision, section 37 consent, Electricity Act 1989
To dismantle an existing tower and build a new 9 metre tower with 2 H poles and associated overhead electricity lines.
Applies to England
Documents
Details
To dismantle an existing tower and build a new nine metre tower with two ‘H’ poles and associated overhead electricity lines, at Aller Court Solar Park. Screening decision, section 37 consent, Electricity Act 1989.
Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
21 June 2023
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.