Alwyn East Development
Project Summary
Documents
Details
Alwyn East Development - TotalEnergies E&P UK Ltd - 2021 - D/4264/2021 Determined
Key Dates
- Date Environmental Statement received by the department - 23/09/2021
- Public notice commencement date - 22/10/2021
- Public notice closing date - 22/11/2021
- Further information public notice commencement date -
- Further information public notice closing date -
Environmental Statement & associated documents
- Summary of the Project – Received Date 23/09/2021
- Environmental Statement – Received Date 23/09/2021
- Public Notice – Received Date 22/10/2021
Further Information
- Secretary of State request for provision of further information – Issued Date 04/02/2022
- Developer response to Secretary of State request for provision of further information – 08/04/2022
- Further information public notice –
Decision made by Secretary of State
- Secretary of State notice under regulation 16(1) – 22/09/2023
- Secretary of State decision to agree to or refuse to agree to the OGA granting of consent - Letter to the developer – 13/10/2022
- Additional Secretary of State letter to the OGA to agree to the granting of the consent under the new Production Consent reference number - 04/09/2023
- Secretary of State decision to agree to or refuse to agree to the OGA granting of consent – 11/10/2022
Updates to this page
Last updated 24 November 2023 + show all updates
-
Date of developers response to Regulation 12(1) Notice uploaded.
-
Date of Secretary of State Regulation 16(1) Notice was incorrect and has been amended.
-
Telephone number was incorrectly redacted in Regulation 16(1) Notice. The only change to the Regulation 16(1) Notice was to insert telephone number.
-
Decision document and associated letters uploaded; Decision dates entered.
-
Addition of Regulation 12(1) Notice for further information and associated dates
-
First published.