Decision

AQUIND Limited interconnector: development consent order under the Planning Act 2008

Decision by the Secretary of State on an application by AQUIND Limited for construction of an interconnector.

Applies to England

Documents

Decision by Secretary of State on Aquind interconnector (link to National Infrastructure Planning site)

Details

Decision by the Secretary of State on an application by AQUIND Limited for the construction and operation of the UK elements of a bi-directional subsea electrical power transmission link (an interconnector) between the UK and France.

Date of decision

20 January 2022

Company / location

AQUIND Limited
From the boundary of the EEZ in the English Channel to Lovedean in Hampshire, via a landfall at Eastney on Portsea Island, Portsmouth

Type of project

Development consent order for an interconnector under the Planning Act 2008.

Maximum output

Not applicable.

Updates to this page

Published 20 January 2022

Sign up for emails or print this page