Decision

Breach Farm, new poles supporting overhead electricity line: Screening decision, s37 consent, Electricity Act 1989

Install 4 new wooden poles supporting a 132kv overhead line at Breach Farm.

Applies to England

Documents

Details

To install 4 new wooden poles supporting a 132kV overhead line at Breach Farm.   Screening decision – section 37 consent, Electricity Act 1989. 

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

28 July 2023

Section 37 consent to install or keep installed an electric line.

Updates to this page

Published 28 July 2023

Sign up for emails or print this page