Decision letter and Inspector’s Report for a called-in application for the construction of up to 287,909 metres squared (m2) (gross internal) of employment floorspace (Use Class B8 and B1(a) offices) including change of use of Bradley Hall Farmhouse to B1 (a) office use (335 m2) and associated servicing and infrastructure including:
- car parking and vehicle and pedestrian circulation
- alteration of existing access road into site including works to the M6 J20 dumbbell roundabouts and realignment of the existing A50 junction
- noise mitigation
- earthworks to create development platforms and bunds
- landscaping including buffers
- creation of drainage features
- electrical substation
- pumping station
- ecological works