Cambo Phase 1 Field Development
Project Summary
Documents
Details
Cambo Phase 1 Field Development - Siccar Point Energy E&P Limited - 2021 - D/4261/2021 - Under review
Key Dates
- Date Environmental Statement received by the department - 01/06/2021
- Public notice commencement date - 11/06/2021
- Public notice closing date - 10/07/2021
- Further information public notice commencement date -
- Further information public notice closing date -
Environmental Statement & associated documents
- Summary of the Project - Received Date 01/06/2021
- Environmental Statement - Received Date 01/06/2021
- Public Notice - Received Date 07/06/2021
Further Information
- Secretary of State request for provision of further information - 04/08/2021 & 01/02/2022
- Developer response to Secretary of State request for provision of further information - 30/08/2021 & 19/12/2022
- Further information public notice -
Decision made by the Secretary of State
- Secretary of State notice under regulation 16(1) -
- Secretary of State decision to agree to or refuse to agree to the OGA granting of consent - Letter to the developer -
- Secretary of State decision to agree to or refuse to agree to the OGA granting of consent -
Updates to this page
Last updated 22 December 2022 + show all updates
-
Confirmation that response received from developer to Regulation 12(1) letter.
-
Addition of Regulation 12(1) Notice for further information document and associated dates to the 'Further Information' section of the page
-
Regulation 12(1) Notice for further information published.
-
Public Notice commencement date amended.
-
new public notice added
-
Addition of Public Notice and details, upload of copy Summary of Project and copy Environmental Statement
-
First published.