Chambers Farm overhead line, S37 Consent, Electricity Act 1989
Screening decision to add a third wire to 640m of existing 11kV overhead line, replace existing transformer and wood poles, add new pole and additional stays.
Applies to England
Documents
Details
Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017:
- to add a third wire to 640m of existing 11kV overhead line
- replace existing transformer to support single phase to 3 phase
- replace 5 wood poles
- erect an additional pole to aid the transformer upgrade
- add 3 additional stays
Date of decision
4 December 2024
Location
Chambers Farm
Cotswolds
Gloucestershire
England
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.