Clun, Shropshire - overhead line screening decision, s37 consent, Electricity Act 1989
Screening decision to upgrade an 11 kv overhead electricity line in an Area of Outstanding Natural Beauty.
Applies to England
Documents
Details
To upgrade an existing high voltage 11 kv overhead electricity line in an Area of Outstanding Natural Beauty in Shropshire.
Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
6 November 2023
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.