Compliance Audit - Checklist Aid 2020, accessible version
Updated 1 March 2021
Introduction
The Capital Funding Guide, the contract with Homes England and the prospectus are what set the requirements providers should be guided by at all times when delivering a particular programme funded by Homes England.
The Compliance Audit checklist is designed to test that key contractual requirements and funding conditions have been met. It is revised annually and the set of questions for the forthcoming Compliance Audit programme is published on the CA website in advance of the start date.
During the audit, the Independent Auditor checks each scheme for compliance using questions from Homes England published Compliance Audit checklist.
This guide is intended to support providers and independent auditors, during the audit process for the SOAHP. It is however not intended to be used as a guide to contractual requirements and funding conditions. For guidance on these providers need to refer to the Capital Funding Guide, their contract and programme prospectus.
The purpose of this document is to assist providers in making available the required documentation and evidence to independent auditors and to assist independent auditors in ensuring they have sufficient documentation and evidence to answer the questions in the Compliance Audit checklist. The content covers a selected number of questions from the Compliance Audit checklist, specifically those where more breaches have occurred in previous years.
Categories in CA Checklist
General
Scheme file; Cost data; Planning obligation; Scheme details; Variations
Development Stage: pre-development
Valuation - excluding ‘works only’ schemes
Development Stage: development
Secure legal interest; Good title; Building contract; Contractual possession of the site; Insurance
Development Stage: post-development
The completion certificate; Insurance for the completed scheme; Rents; Planning consents; Management Agent & URB checks
Specific programme: Sale
Shared Ownership - Lease agreement; Affordability assessment; Eligibility requirements
Specific programme: Strategic partnership
Financial Audit outcome; Scheme details in IMS
Specific programme: Specialised housing
The property’s previous tenure; Homes England standard definitions, for example Travellers pitches; Restriction on title
Specific programme: Move On
Standards
Specific programme: Care and support specialised housing fund Phase 2 (CASSH2)
Standards; Residents; Service Charges
Additional
Contract requirements
Submitting findings - good practice guide
Less is more
Attachments are required only to support specific audit findings or to evidence any mitigating circumstances. There is no requirement to upload the complete scheme file as a matter of course.
Use your time wisely
Plan for additional time to find necessary evidence should the scheme file happen to be incomplete.
Communicate
Independent Auditor, although not allowed to discuss findings with the provider, should ask additional questions if provided evidence raises any doubts.
Stay focused
The Providers should take time to read IA findings as soon as they are submitted in the CA system.
They should use the 10 days window to add any additional comments or missing evidence. Please be aware that this is the last chance the Providers can influence audit outcome.
Supporting Evidence
The following information discusses in more details specific requirements and suggest where to store or look for the evidence that is being checked during Compliance Audit programme
For some questions, accuracy of the details held in IMS is checked by comparing them against data held in a Scheme File
For other questions, a validation of contract documents, valuations and other key documents held on file is investigated and then compared against grant payment dates.
Question 1: Has a comprehensive scheme file been provided containing all relevant documents as set out in the CFG? If no, please provide details of what documents are missing.
Requirement: CFG - Programme Management - Reporting and audit requirements - 7.3.4 comprehensive scheme file
Evidence: Scheme file
Scheme file should consist of all documents that relate to a particular scheme.
It should evidence the scheme progress and changes which occurred through the scheme development timeframe.
The list of documents vary depending on programme type and processing route, therefore special attention should be given to this by providers when compiling scheme records.
Examples
- Insurance Certificates
- Purchase Contract
- Financial Data
- Market Valuation Report
- Rental Valutation Report
- Planning Permission
- Building Contract
- Key Cost Data (Actual vs Estimate)
- Records of Scheme details i.e. number of homes, unit sizes, scheme type, tenure type
Question 2: Does key cost data entered in the system, along with any updates, match scheme file evidence?
Requirement: CFG - Programme Management - Scheme administration and data collection
Evidence: IMS vs Scheme file
IMS steps: Profile Scheme → Profile → Scheme Costs
Changes to schemes’ actual costs should be recorded within IMS once known. There is the facility to change the variables at the milestone stages of start on site and practical completion even if grant has been paid.
IMS guidance about scheme / profile changes at IMS scheme processing(pages 45 to 52).
Question 3: Is evidence available to confirm that submitted scheme details of number of homes, scheme types, tenure type, size, needs categories, occupancy and location accord with the approved scheme details and those held on file?
Requirement: CFG - Programme Management – Changes to agreed allocations
Evidence: IMS vs Scheme file (IMS submission against building contract details, scheme approval and PC approval)
IMS steps: Profile Scheme → Profile → Unit Details → Double click on Unit ID → Unit Detail
There is the facility to change the variables during the life of the scheme, and at milestone stages. The nature of the change will determine whether it needs the approval of Homes England.
Providers need to update IMS as and when plans change. See IMS guidance about scheme / profile changes at IMS scheme processing.
Question 8: Is there a valid valuation report for the site/property acquired, undertaken by an independent valuer with an appropriate RICS qualification? If no valid valuation or valuation not required, please provide details.
Requirement: CFG - Programme Management - Reporting and audit requirements - 7.3. Audit Requirements
Evidence: Scheme file
A valuation is required even for historic purchases
Written confirmation that an out of date valuation remains valid would be sufficient provided that it is an official letter from the valuer.
Valuations should be carried out by an independent, RICS accredited / registered valuer
This registration provides the necessary professionalism, independence,quality assurance, consistency and ethical standards and provides overarching regulatory requirements.
Valuations should be carried out in accordance with the RICS Red Book which setsout the standards to be followed
In addition, any other relevant RICS guidance should be adhered to. For example, they have issued various practice notes in the last couple of months to account for the COVID-19 implications and what processes can be followed that would still meet with RICS requirements and standards.
Question 9: For owned and leased properties, has the provider obtained secure legal interest, as defined in the Contract /CFG? For AHP, the provider must obtain secure legal interest prior to first grant claim. For Strategic Partnerships, the provider must obtain secure legal interest before the Site is made active in the system. If no, please provide details.
Requirement: CFG –Finance –Grant Claims and Payments –3.1
Evidence: IMS vs Scheme file
IMS steps: Profile Scheme → Profile → Scheme ID → View/Edit Milestones
The contractor must have entered into a legally binding contract covering the whole of the works required for the development. A letter of intent is not acceptable.
Secure legal interest must be in the exact name of the party claiming the grant. Exception to this see CFG (10. Finance / 3. Grant claims and payments / 3.5 Start on Site –grey areas)
Question 11: Have both of the following been achieved prior to Start on Site claim / the main building contract has been signed and dated / contractual possession of the site has passed to the contractor?
Requirement: CFG – Finance – Grant Claims and Payments – 3.4
Evidence: IMS vs Scheme file
IMS steps: Profile Scheme → Profile → Scheme ID → View/Edit Milestones
Start on site
The start on site or first tranche grant claim, which applies as a payment event only to eligible schemes delivered by eligible providers where start on site is achieved, is triggered by the date when:
- the provider and the building contractor have entered in to a building contract
- the building contractor takes possession of the site or property
- the works have commenced
For purchases of empty homes on the open market (‘Existing Satisfactory’ or ‘Purchase & Repair’), if the works are being carried out by in-house organisation, then we would advise that start on site would be when a schedule of works is agreed and can be evidenced, possession of the property has been secured and works have commenced.
Question 15: For Affordable and Social Rent, Rent to Buy and Specialist Rent properties – do rents being charged meet the requirements set out in the CFG? If rents charged do not meet the requirements, please provide details. If no, please explain the reasons, or write “not an Affordable or Social Rent, Rent To Buy or Specialist Rent scheme” as appropriate.
Requirement: CFG - Housing for Rent
Evidence: Scheme file
Social Rent policy is subject to the Regulator’s Rent and Tenancy standards and, social rent levels should be calculated according to a formula based on relative property values and relative local earnings.
Social rents are calculated using the formula and data set out in the Ministry of Housing, Communities and Local Government’s Guidance on Rent for Social Housing (for local authorities), and in The Regulatory Framework for Social Housing in England from 1 April 2015 - and the Rent Standard (including the Rent Standard Guidance) in The Regulatory Framework for Social Housing in England from 1 April 2015 for private registered providers.
Affordable Rent
The maximum rental level for Affordable Rent should be no more than 80% of gross market rent (inclusive of service charges). More detailed information on Affordable Rents can be found at The Regulator of Social Housing’s Rent Standard (April 2020) -paragraphs 3.10 to 3.14 and Policy statement on rents for social housing, chapter 3
Question 16: For Affordable and Social Rent and Rent To Buy and Specialist Rent properties - do rent figures entered in the system correspond to the rents charged? If no, please explain the reasons, or write “not an Affordable or Social Rent, Rent To Buy or Specialist Rent scheme” as appropriate.
Requirement: CFG – Programme Management - Scheme administration and data collection
Evidence: IMS vs Scheme file
IMS steps: Profile Scheme → Profile → Unit Details →Double click on Unit ID → Rent
Providers are required to enter weekly rents into IMS, which are then converted into annual rents in slightly different ways depending on the programme and tenure for slightly different purposes.
The compliance audit check should just be comparing the weekly rent providers enter with the weekly rent that they are charging.
Please read further info below for more details.
IMS rent calculations
It is not the intention that any of these IMS calculations should have an effect on the provider’s rent setting policy, or that they have to use their annual rent to calculate their weekly rent on the same basis as IMS does.
For SOAHP 16-21, for rent properties, the provider is required to enter the weekly rent for the property according to what they are charging.
For compliance audit purposes, as long as the provider can ‘show their working’ and provide the rent conversion/ calculation figure for any discrepancy between the rent in the system and the rent being charged then this should not result in a breach.
Question 16
Checklist category
Post-development
Question text
For Affordable and Social rent and rent To Buy and Specialist rent properties - do rent figures entered in the system correspond to the rents charged? If no, please explain the reasons, or write “not an Affordable or Social rent, rent To Buy or Specialist rent scheme” as appropriate.
AHP 15-18
The system uses 52.12 weeks (this is hard coded) to calculate the annual rent from the weekly rent that the user enters. This is then used to estimate the net annual rental income from the property.
SOAHP 16-21
The system no longer calculates the annual income from the weekly rent- the user is just asked to enter a weekly rent and we don’t provide any instructions on the conversion calculation to use.
Strategic Partnership Programme
The system asks for users to enter the weekly rent with instructions to use the annual rent and divide by 52.18. The system has no hard coded calculations but the instructions are displayed in bold on the screen where the rent is enter.
Compliance Audit-Checklist changes for 20/21
New Number 2020/21 | Old Number 2019/20 | Checklist question | Category | Changes vs 19/20 |
---|---|---|---|---|
N/A | 9 | Were all IMS scheme details submitted in accordance with published guidelines set out in the relevant contract and CFG? If no, please give details. | Pre-development | Deleted |
19 | N/A | Is there a managing agent? | Post-development | New |
23 | N/A | Does the scheme include any Shared Ownership units? | Sale | New |
28 | N/A | Were all scheme/phase details submitted in accordance with published guidelines set out in the relevant contract and CFG? If no, please give details. | Strategic Partnerships | New |
29 | N/A | Has a financial audit been completed on this site? If yes, please provide details of any findings/ issues identified | Strategic Partnerships | New |
N/A | 29 | Supported housing/housing for older people -Do the client groups housed reflect the published group definitions? If no, please provide details | Specialised Housing | Deleted |
32 | N/A | Traveller pitches -has the contractual requirement for providers to register a restriction on title with Land Registry, indicating a requirement to gain Homes England consent to dispose, been met? If no, please provide details | Specialised Housing | New |
33 | N/A | Move On -Does the scheme offer the required type of accommodation? | Move On | New |
34 | N/A | Move On -(For schemes providing accommodation to survivors of domestic abuse) Does the scheme comply with the ‘Move On Standard’? | Move On | New |
N/A | 34 | Has the contractual requirement to register a restriction on title with Land Registry, indicating a requirement to gain Homes England consent to dispose, been met? | Platform for Life and Homelessness Change | Deleted |
If you have any questions, email us at:ComplianceAudit@HomesEngland.gov.uk