Corby to Eaton Socon overhead line, S37 Consent, Electricity Act 1989

Screening decision to rebuild approximately 1.2km of an existing 132 kV overhead line.

Applies to England

Documents

Details

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

26 June 2024

Location

Corby to Eaton Socon

Section 37 consent to install or keep installed an electric line.