Decision

Cottam Solar Project: development consent order, Planning Act 2008

Decision by the Secretary of State on an application by Cottam Solar Project Limited for a solar farm between Lincolnshire and Nottinghamshire.

Applies to England

Documents

Cottam Solar Project decision (link to Planning Inspectorate site)

Details

Decision by the Secretary of State on an application by Cottam Solar Project Limited for the construction, operation, maintenance, and decommissioning of 4 ground mounter solar photovoltaic generating stations, including 4 substations, a battery energy storage system, grid connection and associated infrastructure.  

Date

5 September 2024

Company / location

Cottam Solar Project Limited
Unit 25.7 Coda Studios
189 Munster Road
London
SW6 6AW

Maximum output

Up to 600MW.

Updates to this page

Published 5 September 2024

Sign up for emails or print this page