Decision

Dogger Bank A and B Offshore Wind Farm - Variation 6

Details of ‘Dogger Bank A and B Offshore Wind Farm - Variation 6

Documents

Notice of Variation 6 Schedule 10

Notice of Variation 6 Schedule 11

Details

On 17 February 2015 the Secretary of State for Energy and Climate change granted the Dogger Bank Creyke Beck Offshore Wind Farm Order 2015. A Correction Order was subsequently made on 2 October 2015 . An amendment Order was made by the Secretary of State for Business, Energy and Industrial Strategy on 9 April 2019. The pre-application, examination and Development Consent Order (DCO) documents can be found on the Planning Inspectorate Website.

On 23 December 2022, the Marine Management Organisation (MMO) received a request from Dogger Bank Offshore Wind Farm Project to vary the Deemed Marine Licences (DML) contained within Schedules 10 and 11 of the Dogger Bank Offshore Wind Farm Order 2015.

The MMO’s decision was to vary the DMLs as detailed in the Notice of Variations, effective from 25 January 2023.

Updates to this page

Published 25 January 2023

Sign up for emails or print this page