FBS 275 - Priory Farm overhead line, S37 Consent, Electricity Act 1989
Screening decision to upgrade 87m of existing 11kV overhead line from 2 wire to 3, upgrade the existing pole mounted transformer with a 200KVA 3 phase transformer with an additional pole forming an H Pole construction.
Applies to England
Documents
Details
Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Decision to upgrade 87m of an existing 11kV overhead line from 2 wire to 3. Upgrade the existing pole mounted transformer with a 200KVA 3 phase transformer with an additional pole being installed adjacent to the existing pole to form a H Pole construction. Poles may be replaced to support the new line and pole mounted transformer upon assessment.
Date of decision
15 October 2024
Location
South Downs National Park
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.