Grid connection to new power station, Niro Solar Farm, East Devon: screening decision, s37 consent, Electricity Act 1989
Grid connection to a new power station, Niro Solar Farm, 33kw connection.
Applies to England
Documents
Details
To upgrade 3 spans of existing 11 kilovolt overhead electricity line. Screening decision – section 37 consent, Electricity Act 1989.
Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
7 July 2023
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.