Screening decision to upgrade approximately 5 kilometres of existing 11kV overhead from single phase to 3-phase. Replace 27 poles on a like-for-like basis and install a new lazy leg pole next to existing pole 43JFC6 to support a new 200kVA pole-mounted transformer.
Applies to England
Documents
Details
Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
5 March 2025
Location
Hamatethy
Cornwall
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.