Hawthorn Pit overhead line, S37 Consent, Electricity Act 1989
Screening decision to re-align a 132 kV, 304 metre overhead line to facilitate connection to a new 400 kV substation, install a new 132kV tower at a height of 46 metres and install new downleads, connecting the new tower to the substation.
Applies to England
Documents
Details
Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
2 August 2024
Location
Hawthorn Pit
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.