Decision by the Secretary of State on an application by Ecotricity (Heck Fen Solar) Limited for a solar farm in Lincolnshire.

Applies to England

Documents

Heckington Fen Solar Park decision (link to National Infrastructure Planning site)

Details

Decision by the Secretary of State on an application by Ecotricity (Heck Fen Solar) Limited for the construction, operation and decommissioning of a ground mounted solar generating facility with a total capacity exceeding 50 megawatts (MW) together with an energy storage facility (with an estimated storage capacity of 200-400 MW), below ground grid connection to, and extension at, the National Grid Bicker Fen substation.

Date of decision

24 January 2025

Company / location

Ecotricity (Heck Fen Solar) Limited
Lincolnshire

Type of project

Development consent order for a photovoltaic solar farm under the Planning Act 2008.

Maximum output

At least 50 MW – there is no maximum limit on generating capacity.