Heckington Fen Solar Park: development consent order Planning Act 2008
Decision by the Secretary of State on an application by Ecotricity (Heck Fen Solar) Limited for a solar farm in Lincolnshire.
Applies to England
Documents
Details
Decision by the Secretary of State on an application by Ecotricity (Heck Fen Solar) Limited for the construction, operation and decommissioning of a ground mounted solar generating facility with a total capacity exceeding 50 megawatts (MW) together with an energy storage facility (with an estimated storage capacity of 200-400 MW), below ground grid connection to, and extension at, the National Grid Bicker Fen substation.
Date of decision
24 January 2025
Company / location
Ecotricity (Heck Fen Solar) Limited
Lincolnshire
Type of project
Development consent order for a photovoltaic solar farm under the Planning Act 2008.
Maximum output
At least 50 MW – there is no maximum limit on generating capacity.