Hornsea One Offshore Wind Farm variation request
On 10 December 2014, the Secretary of State for Energy and Climate Change granted a Development Consent Order (DCO) for Hornsea One Offshore Wind Farm.
Documents
Details
The pre-application, examination and DCO documents can be found on the planning inspectorate website. In February 2015, DONG Energy Wind Power A/S (“DONG energy”) took full ownership of Hornsea One Offshore Wind Farm.
The DCO authorises DONG Energy to construct and operate up to three offshore generating stations up with a total capacity of up to 1200 MW, within the Hornsea zone. The project is located approximately 120km North-West of the Lincolnshire coast. The development could comprise of up to:
- 332 wind turbine generators
- two offshore accommodation platforms
- five offshore HVAC collector substations
- two offshore HVDC converter stations
- an offshore HVAC reactive compensation substation
- subsea inter-array electrical circuits
- subsea cable connection to the shore
On 30 October 2015, the Marine Management Organisation (MMO) received a request from DONG Energy to vary the Deemed Marine Licence contained within schedule 11 of the Hornsea One Offshore Wind Farm Order 2014 (as amended by The Hornsea One Offshore Wind Farm (Correction) Order 2015). The MMO’s decision was to vary the DML as detailed in the Notice of Variation, effective from 22 April 2016
Updates to this page
Last updated 26 April 2016 + show all updates
-
Documents added
-
Screening opinion added
-
MMO acknowledgement of Hornsea variation request letter added
-
First published.