HS2 Phase 2a: High Speed Rail (West Midlands to Crewe) Act 2021 Schedule 17
Information and guidance to all planning authorities that will determine a request for approval under Schedule 17 to the Act.
Applies to England, Scotland and Wales
Documents
Details
Schedule 17 to the High Speed Rail (West Midlands to Crewe) Act 2021 allows the Secretary of State for Transport to issue statutory guidance to planning authorities about the exercise of their functions under Schedule 17.
Planning authorities are required to have regard to this guidance when considering a request for approval made under Schedule 17 to the Act.
This document provides further information and guidance to all planning authorities that will determine a request for approval under Schedule 17 to the Act.
It also highlights the main differences in the processes and controls conferred to planning authorities under Schedule 17 and the powers they use to routinely determine planning applications under the Town and Country Planning Act 1990.
Updates to this page
Published 5 May 2021Last updated 20 November 2023 + show all updates
-
Scope of Schedule 17 and planning conditions updated.
-
First published.