Decision

James Farm overhead line, Winsor, S37 consent, Electricity Act 1989

Screening decision to upgrade 509 meters of an existing 11kV overhead line from single to 3 phase.

Applies to England

Documents

Details

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

22 March 2024

Location

James Farm
Winsor

Section 37 consent to install or keep installed an electric line.

Updates to this page

Published 22 March 2024

Sign up for emails or print this page