Letcombe Bower line upgrade screening decision, S37 consent, Electricity Act 1989
Screening decision to upgrade 3.3km of existing 11kv overhead lines to 3 phase. Replace and relocate 1x’s pole with a new H terminal pole.
Applies to England
Documents
Details
To upgrade 3.3km of existing 11kv overhead lines to 3 phase. Replace and relocate 1x’s pole with a new H terminal pole. Screening Decision – section 37 consent, Electricity Act 1989.
Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
21 November 2023
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.