Little Horsted substation connection: Compulsory Purchase Order
Decision by the Secretary of State on the compulsory purchase of Little Horsted substation.
Applies to England
Documents
Details
Decision by the Secretary of State to authorise National Grid Electricity Transmission (NGET) the compulsory acquisition of land and rights in land required for the construction and operation of a new grid supply point substation.
Date of decision
4 May 2023
Company / location
Little Horsted
junction of Eastbourne Road
Sussex
Type of project / consent requested
Compulsory Purchase Order under the Electricity Act 1989 and Acquisition of Land Act 1981
Maximum output
Not applicable