Lostock sustainable energy plant: scoping opinion for Environmental Impact Assessment – variation to s.36 consent, Electricity Act 1989
Scoping opinion for Environmental Impact Assessment regarding an application to increase the maximum waste throughput.
Applies to England
Documents
Details
Secretary of State’s scoping opinion for Environmental Impact Assessment (EIA) regarding an application to increase the maximum waste throughput, in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
12 May 2021
Company / location
Lostock Sustainable Energy Plant Limited
Works Lane
Northwich
Type of project / consent requested
Scoping opinion for Environmental Impact Assessment regarding an application to increase the maximum waste throughput.
Maximum output
Not applicable