Decision

Lower Mount Barn overhead line, S37 Consent, Electricity Act 1989

Screening decision to upgrade 807 metres of existing LV/11kV overhead line, upgrade existing pole-mounted transformer and replace 3 existing poles with stout service poles.

Applies to England

Documents

Details

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

27 November 2024

Location

Dorset

Section 37 consent to install or keep installed an electric line.

Updates to this page

Published 27 November 2024