National Grid Electricity Transmission (Scotland to England Green Link 1): Compulsory Purchase Order 2023
Decision by the Secretary of State on a compulsory purchase order application by National Grid Electricity Transmission.
Applies to England and Scotland
Documents
Details
The Order authorises National Grid Electricity Transmission the compulsory acquisition of land and rights in land.
Date of decision
1 August 2024
Location
Scotland to England Green Link 1
Subsea High Voltage Direct Current Link (HVDC)
From Torness in EastLothian to Hawthorn Pit in County Durham
Type of project / consent requested
Compulsory Purchase Order under the Electricity Act 1989 and Acquisition of Land Act 1981.
Maximum output
Not applicable.