Policy paper

National Policy Statement for Nuclear Power Generation (EN-6): volume I

Published 23 June 2011

Applies to England and Wales

Presented to Parliament by the Secretary of State for Energy and Climate Change pursuant to section 5(9) of the Planning Act 2008.

This has been laid together with volume 2 which contains the annexes to the statement.

ISBN: 9780108510823

ID: 2441174 07/11


1 Introduction

1.1 Background

1.1.1 The government believes that energy companies should have the option of investing in new nuclear power stations. Any new nuclear power stations consented under the Planning Act 2008 will play a vitally important role in providing reliable electricity supplies and a secure and diverse energy mix as the UK makes the transition to a low carbon economy.

1.2 Role of this NPS in the planning system

1.2.1 This National Policy Statement (NPS), taken together with the Overarching National Policy Statement for Energy (EN-1), provides the primary basis for decisions taken by the Infrastructure Planning Commission (IPC) on applications it receives for nuclear power stations (as specified at Section 1.9 of this NPS). The way in which NPSs guide IPC decision making, and the matters which the IPC is required by the Planning Act 2008 to take into account when considering applications, are set out in Sections 1.1 and 4.1 of EN-1.

1.2.2 Applicants should ensure that their applications, and any accompanying supporting documents and information, are consistent with the instructions and guidance given to applicants in this NPS, EN-1 and any other NPSs that are relevant to the application in question.

1.2.3 This NPS may be helpful to local planning authorities in preparing their local impact reports. In England and Wales this NPS is likely to be a material consideration in decision making on relevant applications that fall under the Town and Country Planning Act 1990 (as amended). Whether, and to what extent, this NPS is a material consideration will be judged on a case by case basis.

1.2.4 Further information on the relationship between NPSs and the town and country planning system, as well as information on the role of NPSs, is set out in paragraphs 13 to 19 of Annex A of the letter to Chief Planning Officers issued by the Department for Communities and Local Government (CLG) on 9 November 2009[footnote 1].

1.2.5 Paragraphs 1.2.2 and 4.1.3 of EN-1 provide details of how this NPS may be relevant to the decisions of the Marine Management Organisation and how the Marine Policy Statement and any applicable Marine Plan may be relevant to the IPC in its decision making.

1.3 Relationship with EN-1

1.3.1 This NPS is part of a suite of energy NPSs. It should be read in conjunction with EN-1, which covers:

  • the high level objectives, policy and regulatory framework for new nationally significant infrastructure projects that are covered by the suite of energy NPSs and any associated development (referred to as energy NSIPs)
  • the need and urgency for new energy infrastructure to be consented and built with the objective of contributing to a secure, diverse and affordable energy supply and supporting the government’s policies on sustainable development, in particular by mitigating and adapting to climate change
  • the need for specific technologies, including the infrastructure covered by this NPS
  • key principles to be followed in the examination and determination of applications
  • the role of the Appraisals of Sustainability (see Section 1.7 below) in relation to the suite of energy NPSs
  • policy on good design, climate change adaptation and other matters relevant to more than one technology-specific NPS; and
  • the assessment and handling of generic impacts that are not specific to particular technologies

1.3.2 This NPS does not seek to repeat the material set out in EN-1, which applies to all applications covered by this NPS unless stated otherwise. The reasons for policy that is specific to the energy infrastructure covered by this NPS are given, but where EN-1 sets out the reasons for general policy these are not repeated.

1.4 Future planning reform

1.4.1 Aside from cases where the Secretary of State intervenes, or where the application is not covered by a designated NPS, the Planning Act 2008, as in force at the date of designation of this NPS, provides for all applications for development consent to be both examined and determined by the IPC. However, the enactment and entry into force of the provisions of the Localism Bill (introduced into Parliament in December 2010) relating to the Planning Act would abolish the IPC. The function of examining applications would be taken on by a new Major Infrastructure Planning Unit (‘MIPU’) within the Planning Inspectorate, and the function of determining applications on infrastructure projects by the Secretary of State (who would receive a report and recommendation on each such application from MIPU). In the case of energy projects, this function would be carried out by the Secretary of State for Energy and Climate Change.

1.4.2 If the Localism Bill is enacted and these changes take effect, references in this NPS to the IPC should be read as follows from the date when the changes take effect. Any statement about the IPC in its capacity as an examining body should be taken to refer to MIPU. Any statement about the IPC in its capacity as a decision-maker determining applications should be taken to refer to the Secretary of State for Energy and Climate Change in his capacity as decision-maker; MIPU would have regard to such statements in framing its reports and recommendations to the Secretary of State.

1.5 Geographical coverage

1.5.1 This NPS, together with EN-1, is the primary decision-making document for the IPC when considering development consent applications for the construction of new nuclear power stations on sites in England and Wales that are listed in this NPS. Part 4 of this NPS lists the sites that the government has assessed to be potentially suitable for such development before the end of 2025. None of the sites listed in this NPS are in Scotland or Northern Ireland.

1.5.2 The IPC will not examine applications for nuclear power stations in Scotland. However, energy policy is generally a matter reserved to UK Ministers and this NPS may therefore be a relevant consideration in planning decisions in Scotland.

1.5.3 In Northern Ireland planning consent for all energy infrastructure is devolved to the Northern Ireland Executive, so the IPC will not examine applications for new nuclear power stations.

1.5.4 In the event that a development consent application for a new nuclear power station is submitted to the IPC for a site not listed in this NPS, the IPC would examine the application and make a recommendation to the Secretary of State, who would make the decision for any such application (see Section 2.3 of this NPS).

1.6 Period of validity and review

1.6.1 This NPS will remain in force in its entirety unless withdrawn or suspended in whole or in part by the Secretary of State. It will be subject to review by the Secretary of State to ensure that it remains appropriate. Information on the review process is set out in paragraphs 10 to 12 of Annex A of CLG’s letter of 9 November 2009 (see also paragraph 1.2.4 above).

1.7 The Appraisal of Sustainability

1.7.1 All of the energy NPSs have been subject to an Appraisal of Sustainability (AoS)[footnote 2], incorporating the requirements of the regulations that implement the Strategic Environmental Assessment Directive[footnote 3]. Section 1.7 of EN-1 provides information on the AoS of EN-1.

1.7.2 As explained at Section 1.7 of EN-1, the primary function of the AoSs has been to inform consultation on the NPSs by providing an analysis of the environmental, social and economic impacts of implementing the energy NPSs by granting development consents in accordance with them. Each of the AoSs also includes a non-technical summary for the benefit of non-specialist readers.

1.7.3 The development of this NPS and the assessment of sites has been influenced by the AoS of this NPS (the Nuclear AoS), which itself has taken into account the findings of the AoS of EN-1. The Nuclear AoS has assessed the NPS as a whole as well as each site listed in this NPS. To the extent relevant, the IPC may take account of the appropriate Nuclear Site Reports when determining an application for development consent.

1.7.4 A summary of the main findings of the Nuclear AoS is set out below.

  • EN-6 could bring significant benefits[footnote 4] in meeting the government’s climate change and energy security objectives
  • Possible adverse effects on nature conservation sites of European importance[footnote 5] were identified by the Nuclear Habitats Regulations Assessment (HRA). Further studies will need to be carried out, as part of the project HRA and environmental impact assessment (EIA) processes for individual development consent applications, to determine the significance of the effects and the effectiveness of any mitigation measures
  • Possible significant adverse effects on nationally important nature conservation sites and designated landscapes were identified by the Nuclear AoS. Further studies will need to be carried out, as part of the project EIA process for individual development consent applications, to determine the significance of the effects and the effectiveness of any mitigation measures
  • Key inter-relationships between biodiversity and other sustainability effects were identified. These were most notably in relation to flood risk management, water quality and sustainable communities
  • There is the potential for interactions and cumulative adverse effects on wider biodiversity in relation to water quality and resources, habitat loss and ‘coastal squeeze’[footnote 6] where there is more than one potentially suitable site for new nuclear power in the locality[footnote 7] or as a result of other major development in the area. Such interactions and adverse effects are possible in European Sites in the Severn Estuary and River Wye and the Outer Thames Estuary where there are 2 potentially suitable nuclear sites[footnote 8]. These issues will need to be considered in project level HRAs and EIAs.
  • Effects associated with the management and disposal of hazardous wastes, including radioactive wastes, can affect other sustainability topics[footnote 9]. The significance of these effects can only be determined through studies as part of the project level EIA and HRA
  • There is the potential for positive effects on local employment opportunities. A development consent application should therefore include an assessment of the considerations given to socio-economic as well as environmental issues (see Section 4.2 of EN-1 for further details regarding the EIA and Environmental Statement). This might be especially relevant where there is the potential for cumulative positive effects for economic development at the regional level, for example in the southwest and north-west of England[footnote 10].
  • Significant trans-boundary effects arising from the construction of new nuclear power stations are not considered likely. Due to the robustness of the regulatory regime there is a very low probability of an unintended release of radiation, and routine radioactive discharges will be within legally authorised limits.

1.8 Interaction with the Habitats Directive

1.8.1 EN-6 is a ‘plan’ for the purposes of the Habitats Directive[footnote 11]. Its objective is to facilitate the delivery of new nuclear power electricity generation on some or all of the sites listed in this NPS by the end of 2025.

1.8.2 The government has assessed this NPS (by conducting an HRA) and has concluded that it cannot rule out the potential for adverse effects on the integrity of European Sites adjacent to or at a distance[footnote 12] from each site listed in this NPS. In line with the requirements set out in Article 6(4) of the Habitats Directive the government considered potential alternatives to the plan and nominated sites, and concluded that there were no alternatives that would better respect the integrity of European Sites and deliver the objectives of this plan. Accordingly the government has presented a case for Imperative Reasons of Overriding Public Interest (IROPI) which sets out the rationale for why the plan should proceed given the uncertain conclusions identified by the Nuclear HRA. This can be found at Annex A of this NPS.

1.8.3 The conclusions of the Nuclear HRA, including the examination of alternative plans and the IROPI case, are set out in the Main HRA Report[footnote 13].

1.8.4 Development consents granted by the IPC in accordance with this NPS are ‘projects’ for the purposes of the Habitats Directive. Paragraph 4.3.1. of EN-1 details the consideration that the IPC needs to give in respect of applications for such projects and also the related requirements on developers. If adverse effects on the integrity of European Sites cannot be ruled out in relation to the project at that stage, then the IPC will need to make an assessment in line with the requirements of the Habitats and Species Regulations.[footnote 14] As set out in Annex A, the government’s findings in respect of Article 6(4) of the Habitats Directive and this NPS does not automatically transfer to individual projects. When undertaking a Habitats Regulations Assessment in respect of a project, the IPC should have regard to the government’s findings detailed in this NPS and the Habitats Regulations Assessment on it.

1.8.5 Further information on the requirement for HRA and the consideration of alternatives is set out at Sections 4.3 and 4.4 of EN-1 and Sections 2.3 to 2.5 and Annex A of this NPS.

1.9 Effect of, and infrastructure covered by, this NPS

1.9.1 This NPS has effect in relation to nuclear power generation with a capacity of more than 50 megawatts (MW) on a site listed within this NPS (see Section 2.3 and Part 4 of this NPS).

2 Assessment Principles

2.1 Introduction

2.1.1 Part 4 of EN-1 sets out the general principles that should be applied in the assessment of development consent applications across the range of energy technologies. This Part contains additional policy for when the IPC is considering an application for nuclear development, for example addressing the government’s policy on the need for early deployment of new nuclear power stations, the siting of nuclear power stations, the consideration of alternatives and the management and disposal of radioactive waste.

2.1.2 This Part also explains the relationship between the Regulatory Justification process and the planning regime; and sets out the role of the regulators in the IPC’s consideration of applications for new nuclear power stations and the interaction that will be required between the IPC and relevant regulators.

2.2 Policy on the need for new nuclear power stations and the benefits of early deployment

2.2.1 This section should be read in conjunction with Part 3 of EN-1, within which the government has set out the need for all types of energy NSIPs, including new nuclear power stations. The IPC should therefore assess applications for new nuclear power stations on the basis that the need for such infrastructure has been demonstrated. Section 3.5 of EN-1 provides detail regarding the specific need for new nuclear power stations.

2.2.2 In order to be considered potentially suitable and therefore be listed in this NPS, sites had to be shown to be capable of deployment by the end of 2025[footnote 15] (see Section 2.3 below). However, given the urgent need to decarbonise our electricity supply and enhance the UK’s energy security and diversity of supply, the government believes that new nuclear power stations need to be developed significantly earlier than the end of 2025.

2.2.3 Failure to develop new nuclear power stations significantly earlier than the end of 2025 would increase the risk of the UK being locked into a higher carbon energy mix[footnote 16] for a longer period of time than is consistent with the government’s ambitions to decarbonise electricity supply[footnote 17]. As a result, it would become more difficult and expensive to meet the government’s targets for significant and urgent decarbonisation of the economy and enhanced security of supply (see Part 3 of EN-1).

2.2.4 Therefore, when considering an application for a new nuclear power station that is capable of deployment by a date significantly earlier than the end of 2025, the IPC should give substantial weight to the benefits (including the benefit of displacing carbon dioxide emissions) that would result from the application receiving development consent.

2.2.5 Paragraph 1.1.2 of EN-1 sets out that the IPC must decide an application for energy infrastructure in accordance with the relevant NPSs except to the extent it is satisfied that to do so would result in adverse impacts from the development outweighing the benefits. The fact that a site is identified as potentially suitable within this NPS does not prevent the impacts being considered greater than the benefits.

2.3 Policy on the siting of new nuclear power stations

2.3.1 The Strategic Siting Assessment (SSA) was designed to identify sites in England and Wales that are potentially suitable[footnote 18] for the deployment of new nuclear power stations by the end of 2025[footnote 19].

2.3.2 Having considered all of the sites nominated as well as those identified by the Alternative Sites Study (see Section 2.4 below) the government believes that only those sites listed in Part 4 of this NPS are potentially suitable for the deployment of new nuclear power stations in England and Wales by the end of 2025. This NPS has therefore been designated for the purposes of the Planning Act 2008 in relation to applications for development consent at those sites listed in Part 4. The boundaries of each listed site are shown on a series of maps (at 1:10,000 scale) at Annex C of this NPS.

2.3.3 To reduce the likelihood of further land being needed, and to increase the usability of sites, nominators were encouraged to ensure that the area nominated into the SSA included within it all likely site plans, and all reasonable variations to those plans. The boundary of the nominated area may, however, vary from the site boundary that is proposed for development consent. It was not considered reasonable to expect nominators to have established, at the time of requesting nominations, detailed lay-outs for the whole of their proposed developments, including for example any additional land needed for construction or decommissioning.

2.3.4 The SSA has therefore been carried out on the basis that applications for development consent may also include land additional to the boundary of the listed site for other elements of the power station, such as car parks, access roads or marine landing facilities, or for the construction and/or decommissioning of the nuclear power station.

2.3.5 The government expects the key operational elements of the power station, and in particular the infrastructure that has the potential to directly cause a radiological hazard such as the reactor building (including the associated turbine hall), spent fuel and intermediate level waste stores, to be located within the boundary of the site that was assessed by the SSA. However, the government recognises that flexibility is required to accommodate detailed local level considerations.

2.3.6 Should the IPC receive and accept a development consent application for a new nuclear power station at a site listed within this NPS but at which it is proposed to locate any of the key operational elements[footnote 20] of the power station outside the boundary identified in this NPS, then the IPC should consider this an application for a non-listed site. However, the government would expect this NPS and EN-1 to be important and relevant considerations in determining the application under section 105 of the Planning Act 2008. In particular, given that the application would include land which has been assessed by the Strategic Siting Assessment, the government would expect the conclusions reached in relation to that land to be important and relevant considerations in determining the application.

2.3.7 Should the IPC receive and accept a development consent application for a new nuclear power station on a site no part of which is listed in this NPS the IPC may have regard to this NPS and EN-1 as important and relevant considerations. In particular the IPC should consider whether the non-listed site meets the SSA criteria and is capable of deployment before the end of 2025, where relevant[footnote 21].

2.3.8 If the IPC receives and accepts a development consent application for a new nuclear power station in circumstances falling within paragraph 2.3.6 or 2.3.7, the IPC will examine the proposal and make a recommendation to the Secretary of State[footnote 22]. The Secretary of State will be the decision maker for any such application.

2.3.9 In this situation, references to the IPC in its capacity as a decision-maker determining applications should be taken to refer to the IPC in its role of making recommendations on applications to the Secretary of State for Energy and Climate Change/the Secretary of State for Energy and Climate Change in his capacity as decision-maker.

2.3.10 If applications of the kind described in paragraphs 2.3.6 or 2.3.7 were made, the Secretary of State would also consider whether there was a need to review the SSA criteria and/or conduct a further SSA.

2.4 The government’s assessment of alternatives and the need for the listed sites to be included in this NPS

2.4.1 The SSA assessed sites through a nomination-driven process. The government believes that, before deciding to put forward a site as part of the SSA process, nominators would have considered the strategic merits of the site in comparison to others. It was in the nominators’ best interests to thoroughly consider alternative sites.

2.4.2 In order to aid its consideration of alternative sites the government commissioned a strategic level screening exercise to identify whether there are any other sites in England and Wales that are potentially suitable for the deployment of new nuclear power stations before the end of 2025 which had not been nominated (the Alternative Sites Study).

2.4.3 As a result of the SSA and the Alternative Sites Study, the government does not believe that there are any alternatives to the listed sites that are potentially suitable for the deployment of new nuclear power stations in England and Wales before the end of 2025 (see paragraphs 2.3.1 and 2.3.2 above).

2.4.4 Given the very limited number of sites identified as potentially suitable for the deployment of new nuclear power stations before the end of 2025, the government considers that all 8 are required to be listed in this NPS. This is to allow sufficient flexibility to meet the urgent need for new nuclear power stations (see Part 3 of EN-1) whilst enabling the IPC to refuse consent should it consider it appropriate to do so.

2.4.5 In addition to the consideration of alternative sites, an assessment was undertaken as part of the Nuclear AoS to consider whether or not the objectives of this NPS could be delivered using alternative options (see Section 1.7 of this NPS for further information regarding the AoS and Section 1.7 of EN-1 for information regarding the consideration of alternatives in the AoS of EN-1). That assessment included consideration of not having this NPS, or having an NPS which prohibited new nuclear power stations, and alternative ways of developing this NPS. It is the government’s view that none of the alternative options looked at can be relied upon to deliver the objectives of this NPS by the end of 2025. Further details are set out in Chapters 3 and 4 of the Nuclear AoS Main Report[footnote 23].

2.5 The IPC’s assessment of alternatives

2.5.1 Section 4.4 of EN-1 sets out the circumstances in which the IPC may be required to consider alternative sites or proposals to an application for development consent. In doing so the IPC should act in accordance with Section 4.4 of EN-1 as well as the additional policy set out in this Section 2.5.

2.5.2 In view of the urgent need for new nuclear power stations as set out in Part 3 of EN-1, the IPC should be guided by whether there is a realistic prospect of the proposed alternative being able to generate a comparable amount of low carbon electricity[footnote 24] on a comparable timescale.

2.5.3 The IPC should consider whether a proposed alternative site would meet the SSA criteria (see Section 2.3, Part 4 and Annex C of this NPS) and be capable of deployment before the end of 2025. If not, the government would not expect the site to be important to the IPC’s decision given that it is not an alternative to the sites that are within the NPS[footnote 25].

2.5.4 The government does not believe that there are any alternative sites that meet the requirements of this NPS (see paragraph 2.4.3 above). Further, the government considers that all of the sites listed in this NPS are required to be listed so that they are each available as a potential opportunity for nuclear development subject to the IPC’s consideration of the detailed proposals (see paragraph 2.4.4 above).

2.5.5 Therefore, subject to any contrary legal requirements, the IPC should judge an application on a listed site on its own merits and a comparison with any other listed site is unlikely to be important to its decision.

2.6 The Regulatory Justification process and the planning regime

2.6.1 The Basic Safety Standards Directive[footnote 26] requires European Member States to ensure that all new classes or types of practice resulting in exposure to ionising radiation are ‘justified’ (by their economic, social or other benefits in relation to the health detriment they may cause) in advance of being first adopted or first approved.

2.6.2 This process has been implemented in UK law by the Justification of Practices Involving Ionising Radiation Regulations 2004 (the Justification Regulations) and is known as Regulatory Justification. In relation to nuclear power in the UK, the Justifying Authority for the implementation of the Regulatory Justification aspects of the Basic Safety Standards Directive is the Secretary of State for Energy and Climate Change.

2.6.3 In October 2010 the Secretary of State published his decisions[footnote 27] that 2 nuclear reactor designs, Westinghouse’s AP1000 and Areva’s EPR, are justified[footnote 28].

2.6.4 Given that Justification is a separate regulatory process a decision regarding the grant of development consent should not be delayed in the event that a Regulatory Justification decision is subject to legal challenge. If there are concerns about a challenge to, or the validity of, a Regulatory Justification decision, the IPC should consider whether requirements[footnote 29] should be attached to the Development Consent Order to the effect that the order is conditional on the existence of a valid Regulatory Justification decision.

2.7 Relationship between the regulatory framework for nuclear power stations and the planning regime

2.7.1 This Section should be read in conjunction with Sections 4.10 to 4.12 and 4.15 of EN-1.

2.7.2 As with other major energy infrastructure, the regulators play an important role in ensuring the safety, security and protection of people and the environment in relation to the design, construction, operation and decommissioning of nuclear power stations and the transport of nuclear material. The regulators for the nuclear industry are the Environment Agency (EA), the Office for Nuclear Regulation (ONR)[footnote 30] and the Department for Transport (DfT)[footnote 31] (collectively referred to in this NPS as the Nuclear Regulators).

2.7.3 The licensing and permitting of nuclear power stations by the nuclear regulators is a separate regulatory process which nuclear power stations have to undergo. To avoid unnecessary duplication and / or delay and to ensure that planning and regulatory expertise are focussed on the most appropriate areas, when considering a development consent application the IPC should act on the basis that:

  • the relevant licensing and permitting regimes will be properly applied and enforced
  • it should not duplicate the consideration of matters that are within the remit of the Nuclear Regulators (see paragraph 2.7.4 below); and
  • it should not delay a decision as to whether to grant consent until completion of the licensing or permitting process (see paragraphs 2.7.5 and 2.7.6 below)

2.7.4 Certain matters are for consideration of the Nuclear Regulators and the IPC should not duplicate the consideration of these matters itself. Such matters include the Generic Design Assessment (GDA)[footnote 32] and the site licensing and environmental permitting processes (including in respect of the management and disposal of radioactive waste, the permitting of cooling water discharges, etc)[footnote 33]. The Nuclear Regulators are also responsible for those matters listed in paragraph 3.5.3 of this NPS.

2.7.5 Applicants should have involved the Nuclear Regulators early enough during the pre-application stage so that they have had the opportunity to incorporate the relevant regulators’ requirements in proposals where appropriate. However, the IPC can still consider and determine an application for development consent where the relevant regulatory licensing, permitting and authorisations process is still in progress, because the IPC can seek and rely on advice from the relevant Nuclear Regulators on whether the necessary licences, authorisations or permits are likely to be issued. Consent should not be refused on the grounds of matters within the remit of the regulators unless the IPC has good reason to believe that any necessary licence, permit or authorisation will not subsequently be granted.

2.7.6 If the regulatory approvals process is incomplete the IPC should also seek advice from the relevant Nuclear Regulators on any regulatory requirements that are likely to be attached and the anticipated timing of these processes and the IPC should liaise with the Nuclear Regulators over any relevant requirements it is considering attaching to a development consent. This is in order to ensure that where possible the requirements attached to a development consent order are consistent with the regulatory approvals process and vice versa.

2.8 Consideration of good design

2.8.1 Section 4.5 of EN-1 sets out the principles of good design that should be applied to all energy NSIPs. In applying these principles to applications for the development of nuclear power stations, the need to ensure the safety and security of the power station, and the need to control the impacts of its operations, must be given substantial weight given the importance of these factors to the operation of a nuclear power station.

2.8.2 For some structures where the functional requirements may change over the lifetime of the structure, such as sea defences, they should be capable of being adapted if the need were to arise in future without major re-design or significant physical disruption (see Section 2.10 of this NPS).

2.8.3 The IPC should consider how good design can act to mitigate the impacts of new nuclear power stations, such as landscape and visual impacts (see Section 3.10 of this NPS and Section 5.9 of EN-1).

2.8.4 The GDA, site licensing and environmental permitting processes will consider certain aspects of design, which the IPC should not replicate (see Section 2.7 above).

2.9 Consideration of combined heat and power

2.9.1 The government’s general policy in respect of combined heat and power (CHP) is set out in Section 4.6 of EN-1.

2.9.2 In keeping with applications for other thermal generating stations, development consent applications for nuclear power stations should demonstrate that the applicant has fully considered the opportunities for CHP.

2.9.3 However, the economic viability of CHP opportunities (see Paragraph 4.6.5 of EN-1 for further details) may be more limited for new nuclear power stations because the application of a demographic criterion for new nuclear power stations can result in stations being located away from major population centres and industrial heat demand. Future industrial, residential or commercial developments may also be constrained to preserve the general characteristics of the area around the nuclear site throughout its lifecycle to ensure that the basis on which the site is licensed is not undermined[footnote 34].

2.10 Climate change adaptation

2.10.1 Part 2 of EN-1 outlines the policy context for the development of energy NSIPs, including policies for mitigating climate change. Section 4.8 of EN-1 sets out generic considerations that applicants and the IPC should take into account to help ensure that new energy infrastructure is resilient to climate change. Additional information that is specific to applications covered by this NPS is set out below.

2.10.2 Nuclear power stations need access to cooling water. As the sites listed in this NPS indicate, this means that nuclear power stations in the UK are most likely to be developed on coastal or estuarine sites. Without appropriate mitigation measures the potential effects of climate change could mean these sites become at greater risk of flooding than if they were located inland (see Section 3.6 of this NPS). Applicants should therefore provide the IPC with information as to how the development incorporates adaptation measures to take account of the effects of climate change, including:

  • coastal erosion and increased likelihood of storm surge and rising sea levels
  • effects of higher temperatures; and
  • increased risk of drought, which could lead to a lack of available process water

2.10.3 Section 4.8 of EN-1 sets out that the ES should take into account how the proposal will take account of the projected impacts of climate change. This should include climate change adaptation.

2.10.4 The GDA process looks at the capability of the power station’s generic design features to take into account the effects of climate change. The subsequent site licensing and environmental permitting processes ensure that new nuclear power stations will be located, constructed, operated and decommissioned with the long-term impacts of climate change in mind.

2.10.5 The relevant Nuclear Regulators will assess the evidence provided by applicants that external hazards to the proposed nuclear power station have been considered. This will include consideration of the reasonably foreseeable effects of climate change over the lifetime of the power station[footnote 35].

2.10.6 Section 2.7 sets out the role of the Nuclear Regulators. The IPC should have regard to advice from the Nuclear Regulators, in particular the ONR and the EA, in relation to climate change impacts and their views on the adaptation measures proposed. Where issues of climate change adaptation fall within the role of the Nuclear Regulators (whether as part of GDA, site licensing or environmental permitting) the IPC should act in accordance with Section 2.7 of this NPS.

2.11 Radioactive waste management

2.11.1 Annex B of this NPS sets out how the government has satisfied itself that effective arrangements will exist for the management and disposal of the wastes produced by new nuclear power stations.

2.11.2 As set out in Annex B, new nuclear power stations will produce a number of different types of waste that will need to be managed in different ways.

  • On the presumption of a once through fuel cycle (and therefore assuming no reprocessing of spent fuel), ‘higher activity waste’ will consist of spent fuel and intermediate level waste. Geological disposal is the way in which higher activity waste will be managed in the long term. This will be preceded by safe and secure interim storage until a geological disposal facility can receive waste.
  • New nuclear power stations will also produce other waste streams: low level waste, liquid and gaseous discharges, and non-radioactive wastes. The government considers that arrangements already exist for the effective management and disposal of wastes in these categories, as demonstrated by the UK’s experience of dealing with such wastes from existing nuclear power stations.

2.11.3 In reaching its view on the management and disposal of waste from new nuclear power stations the government has in particular satisfied itself that:

  • geological disposal of higher activity radioactive waste, including waste from new nuclear power stations, is technically achievable
  • a suitable site can be identified for the geological disposal of higher activity radioactive waste; and
  • safe, secure and environmentally acceptable interim storage arrangements will be available until a geological disposal facility can accept the waste

2.11.4 Given paragraphs 2.11.2 and 2.11.3 above the question of whether effective arrangements will exist to manage and dispose of the waste that will be produced from new nuclear power stations has been addressed by the government and the IPC should not consider this further.

2.11.5 Proposals for waste management facilities[footnote 36] that either form part of the development of the NSIP or constitute ‘associated development’ for the purposes of the Planning Act 2008 should be considered by the IPC in the same way as the rest of the NSIP using the principles and policies set out in EN-1, this NPS and the provisions of the Planning Act 2008. Annex B sets out that other facilities for the interim storage of waste may come forward. However, in the absence of any proposal the IPC should expect that waste would be on site until the availability of a GDF.

2.11.6 The UK has robust legislative and regulatory systems in place for the management (including interim storage, disposal and transport) of all forms of radioactive waste that will be produced by new nuclear power stations. The IPC should act on the basis that the relevant licensing and permitting regimes will be properly applied and enforced (see Section 2.7 of this NPS).

3 Impacts and general siting considerations

3.1 Introduction

3.1.1 Part 5 of EN-1 sets out policy for the IPC when assessing potential impacts which are common across the range of energy NSIPs (generic impacts). It also contains (at Section 5.1) information to inform the interpretation of the impact Sections of all of the energy NPSs.

3.1.2 Part 3 of this NPS provides additional policy for the IPC when assessing the impacts and siting considerations of new nuclear power stations. It should be read in conjunction with EN-1 and also the relevant site assessment set out in Annex C of this NPS, which provides further information in respect of site specific considerations.

3.1.3 While the AoS and HRA reports for each site listed in this NPS contain an assessment of the potential impacts of construction, operation and decommissioning of nuclear power stations at these sites, detailed assessment of the potential impacts of each stage of development will need to take place at the development consent stage (see Section 4.2 of EN-1).

3.1.4 The impacts and siting considerations identified in Part 5 of EN-1 and Part 3 and Annex C of this NPS are not intended to be exhaustive. Applicants are required to assess all likely significant effects of their proposals (see Section 4.2 of EN-1) and the IPC should consider any impacts which it determines are relevant and important to its decision.

3.2 Ownership of sites

3.2.1 The sites listed in this NPS were nominated into the SSA by third parties. Nominators did not have to own the land that they nominated as the ownership of land is a commercial concern that is subject to change.

3.2.2 However, applicants should submit to the IPC up to date information about the ownership and land use of the site, and, where relevant, details of consultation with the owners of the land. Where the land is subject to an alternative use at the time of the application, the IPC should consider that use in conjunction with Section 5.10 (Land Use) of EN-1.

3.3 Impacts of multiple reactors

3.3.1 For the majority of the SSA criteria the number of reactors that may be developed at a site would not affect the outcome of the SSA. However, for criteria where it was more relevant, the assessment was carried out on the basis of one reactor[footnote 37]. The Nuclear AoS also used a base case of one reactor, apart from at Hinkley Point and Sizewell where it assessed twin reactors as a result of nominator proposals.

3.3.2 This does not mean that more than one reactor could not be built at any site, but the impacts of all of the reactors proposed for a site would need to be considered by the IPC (and/or the relevant Nuclear Regulators – see Section 2.7 of this NPS) should such an application come forward[footnote 38].

3.4 Nuclear Impacts

3.4.1 Certain ‘Nuclear Impacts’ are set out in this Part to provide policy that is additional to the generic impacts set out in EN-1 for when the IPC is considering an application for a new nuclear power station. In certain cases, the text in this Part amends the application of policy in EN-1 for this NPS, for example see Section 3.6 (flood risk).

3.4.2 In considering Nuclear Impacts the IPC should also refer to the relevant site AoS and strategic HRA reports, the relevant site assessment set out in Annex C of this NPS, as well as the policy set out in EN-1 (in particular Parts 4 and 5).

3.4.3 The Nuclear Impacts are:

  • flood risk
  • water quality and resources
  • coastal change
  • biodiversity and geological conservation
  • landscape and visual impacts
  • socio-economic; and
  • human health and well being

3.4.4 When considering the Nuclear Impacts the IPC should liaise closely with the Nuclear Regulators in accordance with Section 2.7 of this NPS.

3.5 Flags for Local Consideration

3.5.1 Flags for Local Consideration are siting criteria that were identified through the SSA consultation in 2008, but which it was considered (usually due to the need for detailed site-specific investigations and data) would be more appropriately assessed at the project level[footnote 39].

3.5.2 The Flags for Local Consideration to be considered by the IPC (in accordance with this Part 3) are:

  • proximity to civil aircraft movements
  • access to transmission networks
  • impact on significant infrastructure and resources; and
  • size of site to accommodate construction and decommissioning

3.5.3 Other Flags for Local Consideration (as set out below) will be considered at the time of the development consent application by the ONR (see Section 2.7 of this NPS):

  • demographics
  • seismic risk (vibratory ground motion)
  • capable faulting
  • non-seismic ground conditions
  • emergency planning (the ONR will work together with the local authority or other Emergency Planning Authority)
  • meteorological conditions; and
  • proximity to mining, drilling and other underground operations

3.5.4 As these Flags for Local Consideration are for the ONR rather than the IPC to consider, detailed policy is not set out as planning policy in this NPS[footnote 40].

3.6 Nuclear Impact: flood risk[footnote 41]

Introduction

3.6.1 Generic flood risk impacts of new energy NSIPs are covered in Section 5.7 of EN-1. In addition, policy specific to new nuclear power stations is set out below. It should be noted that the policy set out in Section 5.7 of EN-1 is relevant to applications for new nuclear power stations with the exception of the application of the Sequential Test and Exception Test (see below).

3.6.2 Nuclear power stations need access to cooling water. As the sites listed in this NPS indicate, this means that nuclear power stations in the UK are most likely to be developed on coastal or estuarine sites. Without appropriate mitigation measures the potential effects of climate change make these sites at greater risk of flooding than if they were located inland.

3.6.3 The significance of the effects will depend on the detailed design and site characteristics of the proposed new nuclear power station. In developing this NPS the sustainability of each site in relation to flood risk has been appraised. The AoS reports for individual sites set out the findings, which are also summarised in the Nuclear AoS Main Report. On the basis of the SSA and the Nuclear AoS, it is considered that the listed sites have the potential to be protected from the risks of flooding over their operational lifetime[footnote 42].

3.6.4 The construction of new nuclear power stations could also result in positive effects. For example, measures taken to mitigate the risk of flooding at a new nuclear power station may also protect existing developments in the area.

3.6.5 The Nuclear AoS identified that there are likely to be positive and negative cumulative effects in the south-west and north-west of England, where nominated sites are relatively close to each other[footnote 43].

Applicant’s assessment

3.6.6 In addition to meeting the requirements of Section 5.7 of EN-1, applicants should identify the potential effects of the credible maximum scenario in the most recent projections of marine and coastal flooding and demonstrate that in principle adaptation would be possible.

3.6.7 Applicants must also be able to demonstrate that they could achieve further measures for flood management at the site in the future if future climate change predictions show they are necessary.

3.6.8 Where possible, safety and operational critical installations should be sited in the areas of the site at least risk of flooding.

IPC decision making

The Sequential Test

3.6.9 The Sequential Test (see Section 5.7 of EN-1) has been undertaken by the government as part of the SSA. As a result, the IPC should not conduct the Sequential Test for any of the listed sites – this requirement of EN-1 does not apply to applications for development consent for new nuclear development on any of the sites listed in this NPS. The government has taken a sequential approach to the SSA by assessing all sites at a strategic level, including in relation to flooding, and by using the results of the Alternative Sites Assessment (see Section 2.4 of this NPS). The government has considered whether or not the objectives of this NPS can be met through reasonably available alternative sites in lower flood risk zones.

3.6.10 In conducting the Sequential Test the government concluded that sites within this NPS in lower flood risk zones were not reasonably available alternatives to those in higher flood risk zones. This is because, as set out in paragraphs 2.4.3 and 2.4.4 of this NPS, the government determined that the only potentially suitable sites for the deployment of new nuclear power stations in England and Wales before the end of 2025 are those listed in this NPS; and that all of the sites listed in this NPS are required to be listed to allow sufficient flexibility to meet the urgent need for new nuclear power stations whilst enabling the IPC to refuse consent should it consider it appropriate to do so. The government also notes the advice of the independent regulators that all the sites have the potential to be protected from flood risk throughout their lifetime.

3.6.11 Applicants will still need to submit a flood risk assessment in accordance with Section 5.7 of EN-1. The IPC will need to be satisfied that a sequential approach has been applied at the site level to ensure that, where possible, critical infrastructure is located in the lowest flood risk areas within the site.

The Exception Test

3.6.12 Subject to paragraph 3.6.13 below, the IPC is still required to consider the Exception Test in accordance with Section 5.7 of EN-1 where the site is located in Flood Zone 3 in England (or Zone C in Wales).

3.6.13 As noted at paragraph 3.6.10 above, the government has determined that all of the listed sites are required to be listed in this NPS as being potentially suitable for new nuclear development in spite of some being located in higher flood risk zones, noting that the independent Nuclear Regulators have advised that they have the potential to be protected from flood risk throughout their lifetime, and because of the lack of alternative sites and the need for new nuclear development. As a result, the second limb of the Exception Test[footnote 44] does not apply to new nuclear development.

Mitigation

3.6.14 It is the government’s view, based on the Nuclear AoS and the SSA, that all sites listed in this NPS have the potential to be adequately protected from flood risk (including the potential effects of climate change, taking into account the UK Climate Impacts Programme 2009[footnote 45]).

3.6.15 Based on the advice of the relevant Nuclear Regulators, the IPC should be satisfied that the applicant is able to demonstrate suitable flood risk mitigation measures. These mitigation measures should take account of the potential effects of the credible maximum scenario in the most recent marine and coastal flood projections. Applicants should demonstrate that future adaptation/flood mitigation would be achievable at the site, after any power station is built, to allow for any future credible predictions that might arise during the life of the station and the interim spent fuel stores.

3.6.16 Applicants should set out measures to mitigate the risk of flooding on or from individual sites that may result from the development, including any associated infrastructure such as possible marine landing jetties/docks. For further information on mitigation measures see Section 5.7 of EN-1.

3.7 Nuclear Impact: water quality and resources

Introduction

3.7.1 Generic water quality and resource impacts of new energy NSIPs are covered in Section 5.15 of EN-1. This policy applies to applications for new nuclear development and, in addition, policy specific to new nuclear power stations is set out below.

3.7.2 The Nuclear AoS identified potential adverse effects on water resources including effects on coastal processes, hydrodynamics and sediment transport[footnote 46]. Adverse effects on water resources could occur through increased demand, particularly during construction. The Nuclear AoS also identified indirect effects on nationally and internationally designated habitats, including from the thermal impact of cooling water discharges. This Section should therefore be read in conjunction with Section 3.9 of this NPS and Section 5.3 of EN-1, which set out policy in respect of biodiversity and geological conservation. The significance of these effects depends on the location of the site, proximity to water bodies and the existing water surplus/ deficit status within the region.

Applicant’s assessment

3.7.3 In addition to fulfilling the requirements of Section 5.15 of EN-1, the applicant’s assessment should also set out the characteristics of cooling water for new nuclear power stations and the specific implications of the proposal on marine and estuarine environments.

IPC decision making

3.7.4 The IPC should consider the cumulative effects of a development consent application for the construction of a new nuclear power station at a specific site with other major infrastructure proposals in accordance with the requirements of EN-1 (in particular Section 4.2 of EN-1).

3.7.5 The IPC should liaise closely with the EA who will consider issues of water quality (including any water abstraction and discharge) as part of the environmental permitting process (see Section 2.7 of this NPS).

Mitigation

3.7.6 In the design of any direct cooling system the locations of the intake and outfall should be sited to avoid or minimise adverse impacts on legitimate commercial and recreational uses of the receiving waters, including their ecology. There should also be specific measures to minimise impact to fish and aquatic biota by entrainment or by excessive heat or biocidal chemicals from discharges to receiving waters.

3.7.7 Discharges into water sources will be controlled in accordance with permits issued by the EA. Applicants will be expected to demonstrate Best Available Techniques[footnote 47] to minimise the impacts of cooling water discharges.

3.7.8 The contamination of soils and water resources can be mitigated through the EIA process and managed through the possible implementation of Environmental Management Plans.

3.8 Nuclear Impact: coastal change

Introduction

3.8.1 Generic coastal change impacts of new energy NSIPs are covered in Section 5.5 of EN-1. This policy applies to applications for new nuclear development and, in addition, policy specific to new nuclear power stations is set out below.

3.8.2 The Nuclear AoS identified that the construction of new coastal and fluvial defences and possible marine landing jetties/docks necessary to support the nuclear power station could affect coastal processes, hydrodynamics and sediment transport processes at coastal and estuarine sites. These impacts could lead to coastal erosion or accretion. There could also be changes to offshore features such as submerged banks and ridges and marine ecology.

Applicant’s assessment

3.8.3 In light of the findings of the Nuclear AoS, applicants should assess the site’s geology, soils and geomorphological processes in order to understand the ongoing natural ecological, coastal and geomorphic processes. This will include identifying impacts on coastal processes, intertidal deposition and soil development processes that maintain terrestrial/coastal and/or marine habitats.

IPC decision making

3.8.4 For Oldbury and Hinkley Point, the AoS found that the sites themselves and other schemes which may be proposed in the Severn Estuary could result in cumulative effects[footnote 48]. The possible in-combination effects of such schemes would require more detailed assessment by the IPC should applications for those schemes be sought or granted[footnote 49] as at the strategic level it is not possible to identify whether or not such schemes would have a detrimental impact on coastal change at the listed sites.

Mitigation

3.8.5 In applying the policy on mitigation set out in Section 5.5 of EN-1, and having taken account of the effects of climate change over the lifetime of the project (including any decommissioning period), the IPC should be satisfied that the application will include measures where necessary to mitigate the effects of, and on, coastal change.

3.9 Nuclear Impact: biodiversity and geological conservation

Introduction

3.9.1 Generic biodiversity and geological conservation impacts of new energy NSIPs are covered in Section 5.3 of EN-1. This policy applies to applications for new nuclear development and, in addition, is policy specific to new nuclear power stations as set out below.

3.9.2 The Nuclear AoS has identified potential cumulative ecological effects at sites in the east, south-west and north-west of England[footnote 50]. It also identified some common implications for biodiversity resulting from:

  • water discharge, abstraction and quality issues
  • habitat and species loss and fragmentation/coastal squeeze
  • disturbance events (noise, light and visual); and
  • air quality

Applicant’s assessment

3.9.3 In carrying out an assessment in accordance with Section 5.3 of EN-1, applicants should also consider the effects of the construction of a new nuclear power station on the groundwater regime and its effects on terrestrial/coastal habitats.

3.9.4 At the project level, baseline studies on nationally and internationally important habitats and species that may be affected as a result of the development should be undertaken by the applicant to inform the assessment of the cumulative ecological effects.

IPC decision making

3.9.5 See Section 5.3 of EN-1.

Mitigation

3.9.6 As well as the options for mitigation set out in EN-1, the Nuclear AoS and HRA have identified possible mitigation options. These include variations to building layout to avoid ecologically sensitive areas and on-site measures to protect habitats and species and to avoid or minimise pollution and the disturbance of wildlife.

3.10 Nuclear Impact: landscape and visual impacts

Introduction

3.10.1 Generic landscape and visual impacts of new energy NSIPs are covered in Section 5.9 of EN-1. This policy applies to applications for new nuclear development and, in addition, policy specific to new nuclear power stations is set out below.

3.10.2 The Nuclear AoS identified that the potentially suitable sites share the following landscape issues: the sites are generally in less populated areas that may have value for visual amenity and as landscape resources; they are coastal/estuarine sites; and the scale of the facilities means that the scope for visual mitigation is quite limited. In addition, because of the timescales involved, there is some uncertainty over future land uses once sites are decommissioned.

3.10.3 There is the potential for long-term effects on visual amenity, especially at Sellafield because of the proximity to the Lake District National Park, and at Sizewell, given the Suffolk Coast and Heaths Area of Outstanding Natural Beauty.

3.10.4 Cooling towers may increase a nuclear power station’s visual impact on the landscape. Paragraph 5.9.4. of EN-1 sets out that the IPC should expect the applicant to justify the use of a natural draft cooling system given that the towers are very large and can emit significant steam plumes.

3.10.5 Whilst hybrid cooling systems are significantly shorter, there may be losses of electricity output owing to the energy required to operate them. Given that nuclear power stations are a low carbon source of electricity, the government would not expect such efficiency penalties to offset the negative visual impacts of natural draft cooling towers.

Applicant’s assessment

3.10.6 See Section 5.9 of EN-1.

IPC decision making and mitigation

3.10.7 In assessing the landscape and visual effects resulting from the electricity transmission network associated with the proposal for a new nuclear power station, the IPC should act in accordance with Section 4.9 of EN-1 and with EN-5 (in particular Section 2.8 of EN-5).

3.10.8 The IPC should not expect the visual impacts associated with a new nuclear power station to be eliminated with mitigation. Indeed, the scope for visual mitigation will be quite limited. Mitigation should, however, be designed to reduce the visual intrusion of the project as far as reasonably practicable.

3.11 Nuclear Impact: socio-economic

Introduction

3.11.1 Generic socio-economic impacts of energy NSIPs are covered in Section 5.12 of EN-1. In addition, policy specific to new nuclear power stations is set out below.

3.11.2 EN-1 sets out that the construction, operation and decommissioning of energy infrastructure may have socio-economic impacts. It is noted that nuclear power stations involve large scale construction projects at the beginning of their life. The Nuclear AoS identified that there are likely to be positive effects of local economic significance, although these are less significant at the regional scale except where there are clusters of potentially suitable sites for new nuclear power stations, particularly in the south-west and north-west of England[footnote 51]. There may also be negative effects.

Applicant’s assessment

3.11.3 Through the EIA, and in accordance with Section 5.12 of EN-1, the applicant should identify at local and regional levels any socio-economic impacts associated with the construction, operation and decommissioning of the proposed new nuclear power station.

3.11.4 This assessment should demonstrate that the applicant has taken account of, amongst other things, potential pressures on local and regional resources, demographic change and economic benefits.

IPC decision making and mitigation

3.11.5 See Section 5.12 of EN-1.

3.12 Nuclear Impact: human health and well-being

Introduction

3.12.1 Generic health impacts of energy NSIPs are covered in Section 4.13 of EN-1. This policy applies to applications for new nuclear development and, in addition, policy specific to new nuclear power stations is set out below.

3.12.2 The Nuclear AoS noted that the sites listed in the NPS are on coastal or estuarine locations in rural areas and that there is therefore the potential for impact on land that has recreational and amenity value. As a result, this Section should also be read in conjunction with Section 5.10 of EN-1 (Land Use including Open Space, Green Infrastructure & Green Belt).

3.12.3 The operation of a new nuclear power station is unlikely to be associated with significant noise, vibration or air quality impacts (although there may be local impacts from transport and associated activities during construction; and if cooling towers are required, particularly forced draught towers, the potential noise impact may be greater). With appropriate mitigation, the subsequent effect of these potential impacts on human health is unlikely to be significant.

3.12.4 Radiation from nuclear power stations requires careful management during and beyond the operational life of the power station. However, safety systems in place in the designs of new nuclear power stations and compliance with the UK’s robust legislative and regulatory regime mean that the risk[footnote 52] of radiological health detriment posed by nuclear power stations (both during normal operation and as a result of an unplanned release) is very small[footnote 53], [footnote 54].

3.12.5 In common with other major industrial processes, the construction, operation and decommissioning of new nuclear power stations could affect health care provision. For example, the facility could increase demand on health monitoring services.

3.12.6 The Nuclear AoS also identified that there could be positive effects for health and well being resulting from the positive socio-economic benefits of new nuclear power stations (see Section 3.11 above).

Applicant’s assessment

3.12.7 The applicant should work with the local authority and the local primary care trust (in England) or the Health Board (in Wales) to identify any potentially significant health impacts and appropriate mitigation measures. Where such measures relate to better public information on the extent of risk in relation to radiological hazard, the applicant should consult the Health Protection Agency on the appropriate standards for radiological protection[footnote 55].

IPC decision making

3.12.8 The IPC should consider the positive effect of employment and other socio-economic impacts (see Section 3.11 above) on human health and well being.

3.12.9 The IPC should have regard to the Secretary of State’s Regulatory Justification decision when considering impacts on human health and well being (see Section 2.6 of this NPS).

3.12.10 In accordance with Section 2.7 of this NPS, the IPC should act on the basis that the regulatory regime (including the consideration of demographics as part of the site licensing process) will be properly applied and enforced to protect human health.

Mitigation

3.12.11 The IPC should act on the basis that the risk of adverse effects resulting from exposure to radiation for workers, the public and the environment will be adequately mitigated because of the need to satisfy the requirements of the UK’s strict legislative and regulatory regime as well as the ONR’s implementation of the government’s policy on demographics.

3.13 Flag for Local Consideration: proximity to civil aircraft movements

3.13.1 As part of the SSA, all nominated sites were assessed in relation to their proximity to civil and military aircraft movement and were found to be potentially suitable.

3.13.2 The IPC should consider this Flag for Local Consideration in accordance with the policy set out in Section 5.4 of EN-1. Given the specific security arrangements in relation to air movements around nuclear sites, and the potential impact that new nuclear power stations may have on existing aerodromes and aviation activities, the application should assess the proximity of aircraft movements to the proposed site. Where necessary the IPC should seek the advice of the ONR to ensure that the proposed arrangements sufficiently safeguard the safety of the site.

3.13.3 In accordance with Statutory Instrument 2007 No 1929 (The Air Navigation (Restriction of Flying) (Nuclear Installations) Regulations 2007)[footnote 56] nuclear power stations in the UK are afforded some protection from aviation activity by the establishment of a Restricted Area at each station. Aviation activity within any Restricted Area is limited to that specifically permitted by the Regulations. Typically, such Restricted Areas have a radius of 2 nautical miles and extend vertically to 2,000 feet above the surface. The Regulations will be revised as necessary to take account of any new nuclear power stations.

3.14 Flag for Local Consideration: access to transmission networks

3.14.1 Issues surrounding electricity transmission were not considered in the SSA because not enough information was available to make an assessment at the strategic level and different applicants may come forward with different proposals without affecting the strategic suitability of the site for the purposes of the SSA.

3.14.2 When considering a development consent application pursuant to this NPS, the IPC should refer to Section 4.9 of EN-1 in respect of the grid connection. Applications for above ground electricity lines of 132 kilovolts (kV) and above, and other infrastructure for electricity networks that is associated with a Nationally Significant Infrastructure Project, such as substations and converter stations, will be considered by the IPC using EN-5.

3.15 Flag for Local Consideration: impact on significant infrastructure and resources

3.15.1 Significant infrastructure and resources includes:

  • motorways, major highways (for example A roads)[footnote 57]
  • strategic rail network
  • gas transmission network
  • electricity transmission network
  • airports
  • ports; and
  • Groundwater Source Protection Zones and Drinking Water Protected Areas[footnote 58]

3.15.2 Applications should demonstrate that the proposed development would not have an unacceptable adverse impact on significant infrastructure. The IPC should take into account any local authority impact report, advice from the relevant Nuclear Regulators and relevant policy in NPSs in assessing impacts on significant infrastructure and resources.

3.15.3 In particular, the Nuclear AoS identified that there may be adverse effects during the construction and decommissioning phases on regional transport networks that may already be under stress, particularly where there are clusters of potentially suitable sites for new nuclear power stations. In considering this issue the policy set out in Section 5.13 of EN-1 (Transport and Traffic impacts) applies.

3.16 Flag for Local Consideration: size of site to accommodate construction and decommissioning

3.16.1 Some activities associated with the proposed development may take place outside of the boundaries of the listed site (for example construction and decommissioning activities – see Section 2.3 of this NPS). In considering an application for development consent IPC should assess all impacts of the proposed development that it considers relevant and important to the application in accordance with the Planning Act 2008, the policy set out in EN-1 and this NPS.

4 Potentially suitable sites for the deployment of new nuclear power stations in England and Wales before the end of 2025

4.1 List of potentially suitable sites

4.1.1 The following sites are those that the government has determined are potentially suitable for the deployment of new nuclear power stations in England and Wales before the end of 2025:

  • Bradwell
  • Hartlepool
  • Heysham
  • Hinkley Point
  • Oldbury
  • Sizewell
  • Sellafield; and
  • Wylfa

4.2 The government’s assessment of potentially suitable sites

4.2.1 The sites listed in this NPS have been assessed by the government by way of the SSA (see Sections 2.3 and 2.4 of this NPS). More information about the SSA process and criteria, including what the criteria were and what was considered against them, is available in Annex C.

4.2.2 The range of sources that the government used in coming to its decision as to which sites are potentially suitable for the purposes of the NPS includes:

  • site nominations
  • comments made by the public during the initial opportunity for comment in Spring 2009
  • the Nuclear AoS and HRA conducted at a strategic level for each site and the NPS as a whole
  • responses to the public consultation on the NPS which took place from November 2009 to February 2010
  • advice from specialists such as the Nuclear Regulators, including on the assessment of sites against specific criteria, comments received during the opportunity for public comment in 2009 and the public consultations on the NPS; and
  • Parliamentary scrutiny of the NPS

4.2.3 Annex C to this NPS is comprised of site assessments for each of the listed sites[footnote 59]. These include analysis and conclusions drawn against the SSA criteria and reflect advice received from specialists and the Nuclear Regulators. They also highlight some of the key points made by the public on the site assessments[footnote 60].

Glossary of key terms

Term[footnote 61] Definition
AoS Appraisal of Sustainability
Alternative Sites Study A strategic level screening exercise commissioned by the government to identify all sites in England and Wales that are potentially suitable for the deployment of new nuclear power stations by the end of 2025 that had not been nominated as part of the SSA
AP-1000 A new nuclear reactor designed by Westinghouse that is being assessed as part of GDA
CLG Department for Communities and Local Government
deployment Commencing operation of one or more new nuclear power stations
DECC Department of Energy and Climate Change
DfT Department for Transport
EA Environment Agency
EIA Environmental Impact Assessment
EN-1 Overarching NPS for Energy
EN-5 The NPS for Electricity Networks Infrastructure
EN-6 The NPS for Nuclear Power Generation (or the Nuclear NPS)
energy NPSs The suite of 6 energy NPSs produced by DECC (EN-1 to EN-6)
energy NSIPs Nationally significant energy infrastructure projects, applications for which will be considered by the # IPC in accordance with the energy NPSs
EPR European Pressurised Reactor – a new nuclear reactor designed by Areva that is being assessed as part of GDA
European Sites A network of internationally important sites designated for their ecological status, comprising Sites of Community Importance (SCI), Special Protection Areas (SPAs), Special Areas of Conservation (SACs), candidate Special Areas of Conservation (cSACs) and European Offshore Marine Sites (EOMS). For the purposes of EN-6 this term also includes Ramsar sites and potential SPAs
Flags for Local Consideration Siting criteria that were identified through the SSA process, but which were considered would be more appropriately assessed at the project level
GDA Generic Design Assessment
generic impacts Potential impacts of any energy NSIPs, the general policy for consideration of which is set out in Part 5 of EN-1
Habitats Directive The European Directive (92/43/EEC) on the Conservation of Natural Habitats and Wild Flora and Fauna
HSE Health and Safety Executive. The OCNS, along with the NII, were part of the Nuclear Directorate within the Health and Safety Executive (HSE). The Nuclear Installations Inspectorate was replaced by the Office for Nuclear Regulation (ONR), an agency of the Health and Safety Executive, on 1st April 2011. The government intends to bring forward legislation to bring the ONR outside of the HSE in due course.
HRA Habitats Regulations Assessment
IPC Infrastructure Planning Commission
IROPI Imperative Reasons of Overriding Public Interest (see Annex A of this NPS)
MW Megawatts
NDA Nuclear Decommissioning Authority
NPS National Policy Statement
Nuclear AoS The AoS for EN-6
Nuclear Impacts Potential impacts of new nuclear power stations where additional policy is provided in Part 3 of EN-6 in addition to that set out in EN-1
Nuclear HRA The HRA for EN-6
Nuclear Regulators The EA, the ONR, and DfT (see below).
OCNS, ONR & NII The Nuclear Installations Inspectorate (NII) and the Office for Civil Nuclear Security (OCNS) were part of the Nuclear Directorate within the HSE. The NII was replaced by the ONR, an agency of the Health and Safety Executive, on 1st April 2011. The government intends to bring forward legislation to bring the ONR outside of the HSE in due course.
SSA Strategic Siting Assessment
  1. Letter to Chief Planning Officers: National Policy Statements 

  2. The Appraisal of Sustainability is required by section 5(3) of the Planning Act 2008. See the Appraisal of Sustainability for the Revised Draft Nuclear National Policy Statement: Main Report, 2010, Consultation on the revised draft National Policy Statements for Energy Infrastructure 

  3. Directive 2001/42/EC of 27 June 2001 on the assessment of the effects of certain plans and programmes on the environment as implemented by the Environmental Assessment of Plans and Programmes Regulations 2004 (SI 2004/1633). 

  4. In this NPS the terms ‘effects’, ‘impacts’ or ‘benefits’ should be understood to mean likely significant effects, impacts or benefits (in accordance with Section 4.2 of EN-1). 

  5. The Habitats Directive (see footnote 11) protects habitats and species of European nature conservation importance by establishing a network of internationally important sites designated for their ecological status. These are referred to as Natura 2000 sites or European Sites, and comprise Sites of Community Importance (SCI), Special Protection Areas (SPAs) (as classified under the EC Birds Directive 1979), Special Areas of Conservation (SACs), candidate Special Areas of Conservation (cSAC), and European Offshore Marine Sites (EOMS) designated under the EC Habitats Directive. For the purposes of the Nuclear HRA all SAC, cSAC, SPA, pSPA, EOMS and Ramsar sites are referred to as ‘European Sites’. It is government policy to treat Ramsar sites, designated by the Ramsar Convention on Wetlands (1971) and potential SPAs (pSPAs) as if they are fully designated European Sites for the purpose of considering any development proposals that may affect them (Planning Policy Statement 9 Biodiversity and Geological Conservation; Government Circular: Biodiversity & Geological Conservation – Statutory Obligations and their impact within the planning system (ODPM, 2005); and Technical Advice Note (TAN) 5 Nature Conservation and Planning (WAG, 1996)). 

  6. The reduction in habitat area which can arise if the natural landward migration of a habitat under sea level rise is prevented by the fixing of the high water mark, for example a sea wall. 

  7. See Section 2.3 of this NPS for details of the government’s policy on the siting of new nuclear power stations; and Part 4 of this NPS for the list of sites determined by the government to be potentially suitable for the deployment of new nuclear power stations in England and Wales before the end of 2025. 

  8. The Severn Estuary and the River Wye are both within the vicinity of Hinkley and Oldbury. Bradwell and Sizewell are within the vicinity of the Outer Thames Estuary. 

  9. Appraisal of Sustainability for the Revised Draft Nuclear National Policy Statement: Main Report, 2010, Chapter 6: Radioactive waste, spent fuel and hazardous waste, Consultation on the revised draft National Policy Statements for Energy Infrastructure 

  10. The listed sites that are located in the south-west of England are Hinkley and Oldbury. Heysham and Sellafield have the potential to cause cumulative effects in the north-west of England. 

  11. The European Directive (92/43/EEC) on the Conservation of Natural Habitats and of Wild Flora and Fauna (the Habitats Directive). 

  12. The HRA considered the likely effects of the plan on all those European Sites that were within 20 km of the sites listed in the NPS. Further, in consultation with the Statutory Consultees, the HRA also considered European Sites at a greater distance from the nominated sites where potential impact pathways (e.g. hydrological connectivity) were known to exist. 

  13. Habitats Regulations Assessment of the Revised Draft Nuclear National Policy Statement: Main Report, 2010, Consultation on the revised draft National Policy Statements for Energy Infrastructure 

  14. The Conservation of Habitats and Species Regulations 2010 (SI2010/490), which implement the Habitats Directive and relevant parts of the Birds Directive. 

  15. For the purposes of this NPS ‘deployment’ means commencing operation of one or more new nuclear power stations. 

  16. Analysis suggests that in scenarios of central fossil fuel prices and high fossil fuel prices, if nuclear power was excluded from the energy mix it would be replaced by new gas fired generation. For more details see Chapter 3 of the Nuclear AoS Main Report: Consultation on the revised draft National Policy Statements for Energy Infrastructure 

  17. See EN-1 for details of the government’s climate change strategy. 

  18. The SSA could only conclude that sites are ‘potentially’ suitable as it is a strategic level assessment based on the information available to the government at the time. The IPC will assess the details of each application for new nuclear development in accordance with EN-1, this NPS and the Planning Act in order to determine whether or not to grant development consent at any of the listed sites. To be considered potentially suitable the sites had to meet the SSA criteria (see ‘The SSA criteria and how sites are assessed’ in Volume II of this NPS) and be shown to be capable of deployment before the end of 2025. The SSA also included an assessment of the ability of the site to store spent fuel and intermediate level waste (see Section 2.11 and Annex B of this NPS). 

  19. The government consulted on the SSA process and criteria and issued a response in 2009: Towards a National Nuclear Policy Statement: government response to consultations on the SSA and siting criteria for new nuclear power stations in the UK; and to the study on the potential environmental and sustainability effects of applying the criteria, 2009: Government response to consultations on the Strategic Siting Assessment process and siting criteria for new nuclear power stations in the UK; and to the study on the potential environmental and sustainability effects of applying the criteria 

  20. As described in paragraph 2.3.5. Section 55 of the Planning Act 2008 sets out the circumstances under which the IPC may accept an application for development consent. 

  21. See ‘The SSA criteria and how sites are assessed’ in Volume II of this NPS

  22. Section 74 of the Planning Act 2008 states that where a NPS does not have effect the IPC has the functions of examining the application and making a report to the Secretary of State on the application setting out: (i) the IPC’s findings and conclusions in respect of the application; and (ii) the recommendation as to the decision to be made on the application. The examination is to be conducted in accordance with the provisions of Chapter 4 of Part 6 of the Planning Act 2008. 

  23. Appraisal of Sustainability for the Revised Draft Nuclear National Policy Statement: Main Report, 2010, Consultation on the revised draft National Policy Statements for Energy Infrastructure 

  24. See Section 3.5 of EN-1 which sets out why nuclear power stations are considered to be low carbon. 

  25. See also paragraph 4.4.3 of EN-1 

  26. European Council Directive 96/29/Euratom of 13 May 1996 

  27. Regulatory Justification 

  28. The decisions were taken by the making of Regulations by way of statutory instruments: The Justification Decision (Generation of Electricity by the AP1000 Nuclear Reactor) Regulations 2010 and The Justification Decision (Generation of Electricity by the EPR Nuclear Reactor) Regulations 2010, copies of which are available on Legislation.gov.uk. 

  29. As defined in Section 120 of the Planning Act 2008 

  30. The Nuclear Directorate of the Health and Safety Executive (HSE), which included the Nuclear Installations Inspectorate (NII) and Office for Civil Nuclear Security (OCNS) was replaced by the Office for Nuclear Regulation (ONR), an agency of the HSE, on 1st April 2011. The government intends to bring forward legislation to bring the ONR outside of the HSE in due course. 

  31. The safety of nuclear transports (and security of less sensitive nuclear material) is regulated by the Department for Transport. 

  32. The purpose of the GDA is to provide a robust, transparent and independent review of the ‘licensibility’ of nuclear power station designs. This begins prior to the assessment of other site licensing and environmental permitting issues and before large capital commitments need to be made, thus reducing project risks and uncertainty associated with the regulatory processes. New nuclear power stations 

  33. This includes matters arising from the reports by HM Chief Inspector of Nuclear Installations, Dr Mike Weightman, on the implications of the Japanese earthquake and tsunami for the UK nuclear industry. The interim report was published in May 2011. Dr Weightman has also confirmed that the ONR’s advice on the SSA and NPS has not changed. Dr Weightman’s report focuses on issues relevant to the nuclear licensing and regulatory regimes and are therefore primarily within the regulators’ remit. Update on nuclear situation in Japan

  34. PADHI+ nuclear installations 

  35. Safety Assessment Principles for Nuclear Facilities, p38 paragraph 226 

  36. Such as interim storage facilities that may house higher activity waste prior to ultimate disposal in a geological disposal facility. Geological disposal of higher activity waste from new nuclear power stations is currently programmed to be available from around 2130, although the future optimisation of plans for the implementation of geological disposal and the expected inventory for disposal may provide potential to bring forward this date. See: Geological Disposal Implementation Board (GDIB)

  37. Size of site (D9) and cooling (D10) criteria assessed the impact of one reactor. 

  38. The government would not expect to re-assess a site against the SSA criteria or re-run the relevant AoS and HRA assessments should proposals for more than one reactor be submitted. 

  39. Towards a Nuclear National Policy Statement: Consultation on the Strategic Siting Assessment Process and Siting Criteria for New Nuclear Power Stations in the UK, 2008, p15 

  40. Details regarding these Flags for Local Consideration are set out in the consultation document referenced above. 

  41. This covers flood risk from any source including storm surge and tsunami. 

  42. See ‘The SSA criteria and how sites are assessed’ in Volume II of this NPS

  43. See footnote 10 which identifies the listed sites located in the south-west and north-west of England. 

  44. The second limb of the Exception Test (as set out in the second bullet of paragraph 5.7.16 of EN-1) is that the project should be on developable, previously developed land or, if it is not on previously developed land, that there are no reasonable alternative sites on developable, previously developed land, subject to any exceptions set out in the technology-specific NPSs

  45. UK Climate Projections 

  46. Appraisal of Sustainability for the Revised Draft Nuclear National Policy Statement: Main Report, 2010, Consultation on the revised draft National Policy Statements for Energy Infrastructure 

  47. Best Available Techniques (BAT) are required to be considered (under European law) in order to avoid or reduce emissions resulting from certain installations and to reduce the impact on the environment as a whole. Use of BAT is required by the EA when licensing the major potentially polluting industries. BAT takes into account the balance between the costs and environmental benefits. 

  48. The AoS identifies that there are potential cumulative effects between Hinkley Point and Oldbury and with any potential Severn Tidal Power Project. The government has concluded that it does not see a strategic case for public investment in a tidal energy scheme in the Severn Estuary at this time, but wishes to keep the option open for future consideration. For further details see Severn Tidal Power 

  49. See EN-1 paragraph 4.2.5. 

  50. See footnote 10 which identifies the listed sites located in the south-west and north-west of England. Sites in the east of England are Bradwell and Sizewell. 

  51. See footnote 10 which identifies the listed sites located in the south-west and north-west of England. 

  52. This risk has been considered for all stages of the development – operation, decommissioning and the storage, transportation or disposal of radioactive waste. 

  53. The annual Radioactivity in Food and the Environment (RIFE) report assesses radiation doses received by members of the public from all sources and show that these remain well below the statutory dose limit. RIFE reports are produced jointly by the Environment Agency, the Scottish Environmental Protection Agency, the Department of Environment Northern Ireland and the Food Standards Agency. See in particular Table S1 ‘Radiation doses due to discharges of radioactive waste in the United Kingdom’ and Table S2 ‘Radiation doses due to all sources at major UK sites’: Radioactivity in Food and the Environment (RIFE) reports 

  54. Meeting the Energy Challenge: A White Paper on Nuclear Power, 2008, p80. 

  55. In the event that primary care trusts, Health Boards and/or the Health Protection Agency no longer exist, this paragraph should be deemed to refer to their successor bodies as may be appropriate in the circumstances. 

  56. To be deemed to refer to the Regulations as amended or any successor regulations that may be brought into force following designation of this NPS

  57. This also includes trunk roads and for example, the primary route network. 

  58. Groundwater Source Protection Zones and Drinking Water Protected Areas are defined by the EA to protect sources of public drinking water. 

  59. For an explanation as to why Braystones, Kirksanton and Dungeness have been excluded from the list, see the government response to the Consultation on the Draft National Policy Statements for Energy Infrastructure, 2010, and the government Response to the Consultation on the Revised draft National Policy Statements for Energy Infrastructure, 2011, Consultation on the revised draft National Policy Statements for Energy Infrastructure 

  60. The nominations of sites were published in April 2009 for public comment. Site assessments were then consulted on from November 2009 to February 2010 and from October 2010 to January 2011 

  61. This glossary sets out the most frequently used terms in this NPS. There is a similar list in each of the energy NPSs. The glossary set out in EN-1 will also be useful when reading this NPS