National Waste Programme Quarterly Report: Q1 FY 2020 to 2021
Published 2 December 2020
1. Quarter 1 FY 2020/2021
This report provides a “snapshot in time” of the progress being made within the National Waste Programme (NWP) community to achieve the strategic objectives of the programme. The report provides updates from NDA estate waste producers, including a lookback, focus areas for the next quarter and a status update table on projects; events and significant deadlines for the coming quarter; information on engagement with the NWP’s series of training modules; and updates/changes to the threats/opportunities register. For more information, please contact nwp@llwrsite.com.
2. National Programme Quarterly Update
The Programme Office has successfully closed out the remaining outstanding work from FY19/20, with finalisation of the Discrete Item Précis, publication of the WAC-Explained (WAC-X) resource, and completion of the Scale-up of Waste Management for Decommissioning project. Work on the FY20/21 programme of work has commenced, and the Programme Office has adapted delivery of this programme to accommodate the changes wrought by the COVID-19 pandemic, favouring digital meetings and data calls as opposed to the usual routes of face-to-face meetings and stakeholder workshops. The Programme Office continues to provide support to the Problematic Waste Integrated Project Team, and the data gathering phase of work on the mercury project, which is undertaking a gap analysis on characterisation and containerisation arrangements for contaminated mercury stocks in the UK nuclear industry. The Programme Office Team has also been supporting the development of the NDA Integrated Waste Management (IWM) Programme.
The focus areas for the next quarter are:
- Commencement and delivery of the Waste Culture project.
- Commencement and delivery of the Waste Generator Requirements of the LLW Disposal Service project.
- Conclusion of the Environmental Permit Review.
Peer Review and Peer Assist update:
The Programme Office has held two Peer Assists in Q1. The first of these was with Rolls-Royce Submarine Ltd, which focussed on their waste management process, and the second was with Dounreay Site Restoration Ltd, which was a follow-up to the 2017 Peer Assist exploring progress made on implementation of their Waste Optimisation Programme. The Peer Assists and any associated outputs will conclude and be produced in Q2.
Key meeting update:
Meetings in Q1 were significantly impacted by the COVID-19 pandemic, which led to the cancellation of the April Delivery Overview Group meeting, and the postponement of the inaugural Customer Supplier Forum (which has been delayed to November).
An LLW NWP Board Meeting was held, with discussion and endorsement of the plan for integrating the NWP into the IWM Programme; it was agreed that the meeting would be the last meeting of the LLW NWP Board, with its governance role being transferred to the IWM Steering Group. To ensure continuity, it was agreed that the existing NWP Senior Responsible Owner would perform the same role for the NWP sub-programme under the new IWM Steering Group, and that they would be engaged, as appropriate, through wider governance arrangements in this capacity. Future NWP work programmes will be validated by the IWM Programme Group, and sanctioned through the IWM Steering Group.
3. Waste Management Services Quarterly Update
Waste diversion in Q1 has been significantly reduced due to the COVID-19 pandemic, with no consignments from NDA waste producers for offsite treatment or disposal. Non-NDA estate companies have consigned some VLLW for disposal, but in significantly lower volumes than forecast. This reduced progress can be attributed to waste producer and supply chain resource constraints as organisations adapted to alternative methods of working and the temporary halting of many on-site activities. As of the end of June, the waste characterisation, LLW disposal, and packaging frameworks are operational with constraints; and the supercompactable and metallic frameworks are not currently operational (although these are expected to be operational by the end of July). The customer team is continuing to engage with waste producers to facilitate the production and implementation of restart plans for NDA waste producing organisations, with enabling works underway for resumption of consignments by the end of Q2.
LLW Repository Ltd (LLWR) awarded the replacement Metallic Waste Framework agreement in May. The framework has a four-year duration and enables waste producers across the UK to access the facilities and skills of all six participants via their Customer Contract with LLWR. The customer team has concluded development of the new Customer Relationship Management (CRM) system and are in the process of implementing it. The system will provide consigning organisations with ‘live’ status updates as proposed consignments move through the Waste Enquiry process, significantly reducing lead-times on queries. This piece of work was delivered in response to customer feedback, and ongoing improvement activities within Waste Management Services (WMS). WMS has launched a new Learning from Experience (LFE) Process. The process compliments existing processes at LLWR, waste producer organisations and the supply chain to identify learning, best practice and successes / failures in waste management. The information is reviewed at a monthly committee meeting and relevant learning is selected to be shared with the wider waste community. The outputs are developed into a range of reports, briefs and flash shares and are disseminated through existing NWP and practitioner fora and made more widely available via electronic means.
The focus areas for next Quarter are:
- Roll out changes to the Waste Loading Plan process (reference Customer Notice 2020-014 ‘Proposed Changes To LLWR Waste Loading Plan Review Process’).
- CRM Phase 2 - Consignment Process - User acceptance testing.
- Development of replacement Characterisation Service technical scope.
- Work with Customers and Supply Chain to develop consignment restart schedules.
- Delivery of 3 x refurbished Gemini casks and new ancillary equipment from CIMAT facility in France.
4. Sellafield Ltd Quarterly Update
Q1 operational matters have been dominated by the response to the COVID-19 pandemic. A staged commencement of operations has been progressed, with a significant number of workfaces now operational. On-site LLW waste management operations have been undertaken, with waste collected, processed via internal waste management capabilities and safely stored. No LLW was transferred for treatment or disposal off-site during the quarter. A small amount of VLLW material has been disposed to the on-site landfill capability.
Good progress has been made on a range of transformation activities, including:
- Formalisation of the response to the mis-consignment Board of Inquiry and initiating the setting up of a standalone waste management organisation.
- Recommencement of the Active Demonstrator projects aimed at managing the boundary waste large metallic items removed from the high hazard facilities, and to trial sort and segregation approaches that can be applied to the breakdown of legacy alpha crates and alpha decommissioning operations.
- Implementing changes to the management of several individual waste streams to reflect the LFE from the Soft Bagged Waste Trial.
- Receipt of the bespoke Discrete Item analysis of 12 WAGR boxes from LLWR, which indicates the acceptability of disposal from a radiological perspective. The analysis has been submitted to the Environment Agency (EA) for their review. Further work will be required to address other WAC aspects.
- Several sub-programme tasks of work progressed to support the next phase of PCM drums, that may be suitable for management as LLW. This includes consideration of capacity issues, an update of the BAT, work on the drum selection methodology, and joint work with LLWR regarding the schedule.
- Developing the optioneering approach to establish the location to undertake the required AGR graphite sampling, as well as separate work on the approach to analyse the samples.
- Positive discussions with EA on documented plans to compile the first iterations of the Waste Management Plan (WMP) and Site Wide Environmental Safety Case (SWESC), as required by the EA guidance on requirements for the release from radioactive substances regulation (the GRRs).
- Further development of the BAT study assessing the approach for VLLW management post the filling of the existing on-site landfill capability.
In addition, the Waste Information Form (WIF) template has been populated ahead of scheduled submission early in Q2.
The focus areas for the next Quarter are:
- Commence offsite LLW/VLLW waste shipments.
- Progress the programme of work to take forward the findings of the waste management Board of Inquiry.
- Undertake follow-up engagement with EA and LLWR on the WAGR box assessments.
- Progress the arrangements to complete the required AGR graphite sampling.
- Progress the on-site landfill capability replacement BAT study.
- Progress implementation of the boundary metallic waste and the alpha sort and segregation Active Demonstrators.
5. Magnox Ltd Quarterly Update
As a result of the COVID-19 pandemic, all waste shipments were stopped from 20th March. In addition, all sites were put into a ‘pause’ with minimal staff actual manning the sites; staff with suitable company IT were asked to work from home.
The result is that for Q1, there were no shipments of low activity waste and some delays to the delivery of transformational projects. The joint waste management plan, JWMP18, was issued in April. A meeting was held in May to launch the transformational projects from the JWMP, where possible.
Focus areas for next Quarter:
- Safe return of some staff to sites and the gradual restart of site operations including waste management and decommissioning activities
- Work on high level strategy for continuous reactor decommissioning at Trawsfynydd site, to include characterisation and waste management routes
- Establishment of programme board for the Magnox Waste Management Improvement Programme, development of programme blueprint and consideration of initial proposals from work completed so far.
- Participation in the IWMPG’s sub-group on waste management culture, building on Magnox’s own work in this area
- Start of JWMP re-forecasting process & review of document for significant changes in line with LLWR/NWP guidance
6. Dounreay Site Restoration Ltd Quarterly Update
Operations: LLW plants were shut down into a safe, compliant state at the end of March 2020 as part of the DSRL site response to the COVID-19 pandemic.
This essentially remained the case throughout FY 20/21 Q1, although some preparations for return to plant occupancy were being implemented at end of the Quarter.
Compliance: Fingerprint review is ongoing throughout Q1.
Focus areas for the coming Quarter:
- Restart plants in a controlled manner.
- Resume consignment of compliant LLW for waste processing / disposal, to include a campaign of Encapsulation Plant / D3100 vault disposal operations.
- Preparation of Non-Containerised Waste for off-site diversion via LLWR Framework.
- Complete stored LLW Half Height Isofreight (HHISO) container voidage assessments and prepare Best Practicable Means (BPM) Statements.
- Continue review and revision of Dounreay fingerprints.
7. LLW Repository Ltd (site) Quarterly Update
No consignments dispatched this quarter due to the current COVID-19 pandemic; however, we have taken the opportunity to compile as many consignment packs as possible to allow us to consign almost immediately upon return to site. Working with Service Delivery, the Waste Services Quotations (WSQs) for metals has been extended until December 2020 and for VLLW until February 2021. Upon review of the draft waste consignment paperwork and the Waste Loading Plan for the MAFI Bogies, the haulier has requested an amendment to how the bogies are loaded. The Transport and Logistics Team are looking into this and providing feedback to move forward. Photos were requested of the underneath of the MAFI Bogies, these have been sent to the Transport and Logistics Team to liaise with the haulier to find a resolution. The advice given by the Customer Team was to complete a Waste Enquiry Form (WEN) specifically for the bogies to obtain the most competitive price. Working with Service Delivery, the draft Waste Consignment Information Forms for our Metallic Consignments have been provisionally accepted by Cyclife, pending photos and loading confirmation; this covers 4 consignments for the remainder of the calendar year.
Focus areas for next Quarter:
- Container inspections to be carried out to allow consignment loading and transport to take place.
- Consignment of 2x Direct Grout Facility VLLW containers that were due to be shipped in March 2020.
- Restart of bag assay with Cavendish and subsequent consignments to our Service Provider.
- Consignment of MAFI Bogies.
- Large items from demolition to be assessed and prepared for consignment next year.
- Consignments to commence for Metals.
Forward calendar key dates
- 17/08/2020 LLW NWP Monthly Managers Telecon
- 21/09/2020 LLW NWP Monthly Managers Telecon
- 28/10/2020 LLW NWP Monthly Managers Telecon
Use of NWP Training Modules
- Total e-learning module certificates issued to date is 623; 89 issued this Quarter.
- Total classroom training attendees to date is 91; 0 attendees this Quarter.
- 96% of users rated the training as good or excellent.
- 98% of users would recommend the training to a colleague.
- 95% of users indicated that they will be able to apply the learning.
Performance against priority business changes
- Strategy implementation has commenced for a greater range of LLW / ILW boundary waste and problematic wastes. Progress has been made on integration of radioactive waste strategy. The NWP has successfully transitioned into the NDA IWM Programme. Status – green – project commenced and is on target to deliver on or ahead of schedule.
- There is a detailed understanding of the sustainability of LLW management practice and arrangements, and active action is being taken to improve this. Status – green – project commenced and is on target to deliver on or ahead of schedule.
- Waste informed culture is prevalent across the industry and full LLW management value chain. Status – green – project commenced and is on target to deliver on or ahead of schedule.
- Consignors have easy access to information or specialist advice to enable understanding of acceptance criteria for treatment and disposal services. Status – green – project commenced and is on target to deliver on or ahead of schedule.
- Waste management practice enables agile, efficient and effective waste flow management to support operations, decommissioning and site restoration. Waste management is fully risk-informed, enabling effective management of waste at the LLW / ILW boundary. Status – green – project commenced and is on target to deliver on or ahead of schedule.
- Reliable and appropriate local and national inventories are available that support and underpin decision making. Status – green – project commenced and is on target to deliver on or ahead of schedule.
8. Strategic Threats and Opportunities
The strategic threats on the NWP are:
- Significant waste mis-consignment event causes partial or full closure of diversion or disposal route(s). Current risk level – major. Probability level – 35%.
- Insufficient radiological, non-radiological or volumetric capacity in the supply chain. Or excessive demand for capacity. Current risk level – moderate. Probability level – 35%.
- Insufficient radiological, non-radiological or volumetric capacity at LLWR. Current risk level – major. Probability level – 15%.
- Changes in legislation, governmental policy and regulatory perspective prevents execution of the LLW Strategy. Current risk level – marginal. Probability level - <2%.
- Large volumes of waste from contaminated land remediation generated and managed as lower activity waste. Current risk level – major. Probability level – 15%.
- Stakeholder concerns over radioactive waste management constrain access to existing routes and / or development of new routes and facilities. Current risk level – marginal. Probability level – 10%.
- Global event (such as a pandemic or war) impacts functioning of all parts of the LLW community, waste management and route availability. Current risk level – severe. Probability level – 100% (currently an impacting risk).
The strategic opportunities of the NWP are:
- Positive step change in the sustainability of the supply chain. Opportunity rating – significant. Probability level – 40%.
- Relevant ILW diverted from HAW disposal. Opportunity rating – significant. Probability level – 30%.
- Buffer storage capabilities can be mobilised for contingency situations (only). Opportunity rating – marginal. Probability level – 30%.
- Improved use of transport infrastructure to support management of ILW. Opportunity rating – marginal. Probability level – 10%.
- Fit-for-purpose flexible and agile packaging fleets available for LLW management. Opportunity rating – marginal. Probability level – 30%.
- Management solutions available and in use for complex, challenging and problematic LLW (PW). Opportunity rating – significant. Probability level – 30%.