Nationally significant infrastructure projects: application fees charges from 1 April 2024/25
Updated 24 September 2024
Applies to England and Wales
Applicants are charged for:
- applications for authorisation under sections 52 and 53 of the Planning Act 2008, obtaining information about interests in land and rights of entry
- venue costs, where the Applicant does not provide a venue for a hearing
- a fee to accompany the application (the ‘Acceptance fee’)
- a Pre-examination fee following the appointment of the Inspector(s) initially chosen to examine the application
- an initial payment in respect of the handling of an application (payable at the beginning of the Examination stage, following the Preliminary Meeting)
- a final payment in respect of the handling of an application (payable on completion of the Examination stage)
1. Fee Charges from 1 April 2024
The table below shows the fees payable from 1 April 2024 for existing and new applications. The Infrastructure Planning (Fees) Regulations 2010 and subsequent amendments can be viewed at legislation.gov.uk
Fee in respect of applications for authorisation under sections 52 and 53 | |
---|---|
A request for authorisation under section 52(2) (information about interests in land). | £1,958 |
A request for authorisation under section 53(1) (rights of entry). | £1,958 |
Fee to accompany application | |
---|---|
The Planning Inspectorate must charge the Applicant a fee in respect of the decision by the Secretary of State under section 55 (Acceptance of applications) whether or not to accept the application. The fee must accompany the application. | £8,796 |
Pre-examination fee | |
---|---|
Following a decision under section 61 (Initial choice of Panel or single Inspector) the Planning Inspectorate must notify the Applicant in writing of the Pre-examination fee. The Pre-examination fee is:- | |
Single Inspector | £25,462 |
Panel of two Inspectors | £42,108 |
Panel of three Inspectors | £58,754 |
Panel of more than three Inspectors | £84,214 |
Initial payment in respect of the handling of an application | |
---|---|
Where an examination is handled by a single Inspector | £1,204 per estimated relevant day |
Where an examination is handled by a panel of two Inspectors | £1,915 per estimated relevant day |
Where an examination is handled by a panel of three Inspectors | £2,624 per estimated relevant day |
Where an examination is handled by a panel of more than three Inspectors | £3,996 per estimated relevant day |
Final payment in respect of the handling of an application | |
---|---|
Following notification of the completion of the Examination stage under section 99. The final payment is dependent on the number of days actually required for the examination:- | |
Where a single Inspector has examined the application | £2,409 per relevant day |
Where a panel of two Inspectors has examined the application | £3,831 per relevant day |
Where a panel of three Inspectors has examined the application | £5,249 per relevant day |
Where a panel of more than three Inspectors has examined the application | £7,992 per relevant day |
The initial payment in respect of handling an application is deducted from the final payment.