Decision

Net Zero Teesside Project: development consent order Planning Act 2008

Decision on an application for the onshore elements of a full chain carbon capture, utilisation and storage (CCUS) project.

Applies to England

Documents

Net Zero Teesside Project decision (link to National Infrastructure Planning site)

Details

Decision by the Secretary of State on an application by Net Zero Teesside Power Limited and Net Zero North Sea Storage Limited for the onshore elements of a full chain carbon capture, usage and storage (CCUS) project comprising a number of elements including:

  • a new gas-fired electricity generating station (with an electrical output of up to 860 megawatts) with post combustion carbon capture plant
  • gas, electricity and water connections (for the electricity generating station)
  • a carbon dioxide (CO₂) pipeline network (a ‘gathering network’) for gathering CO₂ from a cluster of local industries on Teesside
  • a high pressure CO₂ compressor station and a CO₂ export pipeline

Date of decision

16 February 2024

Company / location

Net Zero Teesside Power Limited /
Net Zero North Sea Storage Limited
Near Middlesborough

Type of project

Development consent order for the onshore elements of a full chain CCUS project under the Planning Act 2008.

Maximum output

850 GW

Updates to this page

Published 16 February 2024