North Devon, W29 to W35 and Spur to W30B overhead line, S37 consent, Electricity Act 1989
Screening decision to add a third conductor to 800 metres of an existing 11kV overhead line.
Applies to England
Documents
Details
Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
11 April 2024
Location
North Devon Biosphere Reserve
Torridge
Devon
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.