Northern Endurance Partnership Development
Project Summary
Documents
Details
The Northern Endurance Partnership Development - Net Zero North Sea Storage Limited - 2023 – D/4271/2021 – Under Review
Key Dates
- Date Environmental Statement received by the department – 20/09/2023
- Public notice commencement date – 05/10/2023
- Public notice closing date – 06/11/2023
- Further information public notice commencement date -
- Further information public notice closing date -
Environmental Statement & Associated Documents
- Summary of the Project - Received Date 20/09/2023
- Environmental Statement - Received Date 20/09/2023
- Public Notice - Received Date 05/10/2023
Further Information
- Secretary of State request for provision of further information - 10/11/2023 & 25/03/2024 & 21/06/2024
- Developer response to Secretary of State request for provision of further information - 31/01/2024 & 09/05/2024
- Further information public notice -
Decision made by the Secretary of State
- Secretary of State notice under regulation 16(1) -
- Secretary of State decision to agree to or refuse to agree to the OGA granting of consent - Letter to the developer -
- Secretary of State decision to agree to or refuse to agree to the OGA granting of consent -
Updates to this page
Last updated 27 June 2024 + show all updates
-
Upload - Regulation 12(1) Notice for Further Information Request Under the heading ‘Further Information’ and ‘Secretary of State request for provision of further information - 10/11/2023 & 25/03/2024’ add ‘& 21/06/2024’ After ‘Developer response to Secretary of State request for provision of further information - 31/01/2024’ add ‘& 09/05/2024’
-
Addition of ‘Regulation 12(1) Notice for Further Information Request
-
Addition of a Regulation 12(1) Notice for Further Information Request for the Northern Endurance Partnership Development and the addition of the date of the Developer response
-
Environmental Statement Appendices - uploaded
-
First published.