Decision

Overhead electricity line upgrade to 3 phase near Woolstaston, Shropshire: screening decision – section 37 consent, Electricity Act 1989

Screening decision by the Secretary of State for an application for section 37 consent for a proposed development to upgrade an existing 11kV overhead line of 900 metres from single phase to 3 phase.

Applies to England

Documents

Details

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Screening decision by the Secretary of State for an application for section 37 consent for a proposed development to upgrade an existing 11kV overhead line of 900 metres from single phase to 3 phase.

Date of decision

18 November 2021

Section 37 consent to install and keep installed a line.

Updates to this page

Published 18 November 2021

Sign up for emails or print this page