Screening decision by the Secretary of State for an application for Section 37 consent for UK Power Networks to add 2 short spans to a tower supporting the overhead line.
Applies to England
Documents
Details
Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
UK Power Networks
Tower on land near Easton
Norfolk
Date of decision
3 November 2022
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.