Screening decision to install approximately 620 metres of 400kV overhead line onto existing towers and remove four existing towers and 1.05km of 400kV overhead line.

Applies to England

Documents

Details

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

5 March 2025

Location

Stocking Pelham Substation

Section 37 consent to install or keep installed an electric line.

Updates to this page

Published 5 March 2025