Pelham Substation Line Diversion overhead line, S37 Consent, Electricity Act 1989
Screening decision to install approximately 620 metres of 400kV overhead line onto existing towers and remove four existing towers and 1.05km of 400kV overhead line.
Applies to England
Documents
Details
Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
5 March 2025
Location
Stocking Pelham Substation
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.