Pennycrocker Farm, S37 Consent, Electricity Act 1989
Screening decision to upgrade 550 metres of existing 11kV overhead line and replace four spans of existing overhead line with underground cable.
Applies to England
Documents
Details
Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
31 July 2024
Location
Pennycrocker Farm
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.