Research and analysis

Procurement trial case study: Cookham Wood Prison

Procurement trial projects case study report - Ministry of Justice: Cookham Wood Prison (two stage open book).

Documents

Details

The Government Construction Strategy aims to change the relationship between clients and industry. The trial projects perform a central role in delivering the strategy’s sustainable 15-20% reduction in costs.

This report details the outcomes from the Ministry of Justice: Cookham Wood Prison procurement trial project. This project uses a 2 stage open book procurement model and building information modelling (BIM).

Updates to this page

Published 19 July 2013
Last updated 2 July 2014 + show all updates
  1. Case study updated.

  2. First published.

Sign up for emails or print this page