Decision

Roughground overhead line, S37 consent, Electricity Act 1989

Screening decision to install a third wire in an existing 11 kV 1600 metre line and to install a new lazy leg pole to upgrade a transformer to 3 phase.

Applies to England

Documents

Details

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

4 March 2024

Location

Bodmin
PL31 1DE

Section 37 consent to install or keep installed an electric line.

Updates to this page

Published 4 March 2024

Sign up for emails or print this page