Sheringham and Dudgeon offshore wind farm: development consent order Planning Act 2008
Decision by the Secretary of State on an application by Equinor New Energy Limited for the construction and operation of an offshore array of up to 53 wind turbines.
Applies to England
Documents
Details
Decision by the Secretary of State on an application by Equinor New Energy Limited for the construction and operation of an array of up to 53 wind turbines and their foundations, proposed to be located 15.8km and 26.5km north of the Norfolk Coast, with landfall at Weybourne.
Date of decision
17 April 2024
Company / location
Equinor New Energy Limited
1 Kingdom Street
London
W2 6BD
Type of project
Development consent order for an offshore wind farm project.
Maximum output
The combined generating capacity of the extensions will equate to 786MW.