Staythorpe Power Station, EIA scoping opinion: variation to section 36 consent, Electricity Act 1989
Scoping opinion for Environmental Impact Assessment on an application to retrofit the Staythorpe Power Station with post-combustion carbon capture and associated works.
Applies to England
Documents
Details
Secretary of State’s scoping opinion for Environmental Impact Assessment regarding an application to retrofit the existing Staythorpe Power Station with post-combustion carbon capture and associated works, in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date
31 July 2024
Company / location
RWE Generation UK plc
Windmill Hill Business Park
Trigonos
Whitehill Way
Swindon
SN5 6PB
Type of project / consent requested
Request for a scoping opinion from the Secretary of State under Regulation 18 of the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017 in anticipation of an application under Section 36C of the Electricity Act 1989 to vary the Section 36 consent for the Staythorpe Power Station.
Approximate output
1850 MW