Decision

Stedcombe House overhead line, S37 Consent, Electricity Act 1989

Screening decision to add a third conductor to an existing 11kV 225 metre overhead line.

Applies to England

Documents

Details

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

29 May 2024

Location

Stedcombe House
Devon

Section 37 consent to install or keep installed an electric line.

Published 29 May 2024