Details of the application

The Environment Agency has received a variation application for an environmental permit under the Environmental Permitting (England and Wales) Regulations 2016 from NNB Generation Company (HPC) Limited.

Application number

EPR/JP3122GM/V008

Regulated facility type

Water Management Zones and effluent treatment units

Regulated facility address

Construction site at Hinkley Point C power station
Near Bridgwater
Somerset
TA5 1UD

National grid reference discharge point

ST 20375 46165, ST 19792 45158, ST 20500 45218 and ST 19315 46475

Receiving environment

Severn Estuary and Holford Stream

Effluent type

Trade effluent consisting of site drainage and trade effluent consisting of concrete wash water

Volume

Various

The existing permit allows a number of discharges to be made solely during the construction phase at HPC. As parts of the site are completed construction moves on to other parts and the permit needs to be varied to reflect these changes. In particular this variation is being made to:

a) Allow specific additions to site drainage which require an update to the description of existing Activities within Table S1.1 of the permit.
b) Regularise activities that have already commenced but which also require an update to the description of existing Activities within Table S1.1 of the permit.
c) Revise Activity F (within Table S1.1 of the permit), which requires updates across Schedule 1, 3, 4 and 7 of the permit.
d) Include a new Sub-Activity (or equivalent) to the permit, including updates to the relevant Schedules of the permit.
e) Allow other minor amendments including cessation of existing Activities and addition of a new notification mechanism for cessation of Activities.

How to view the application

The application may be viewed online at https://consult.environment-agency.gov.uk/psc/ta5-1ud-nnb-generation-company-hpc-limited-v008

We are following Government advice to manage the risks of Coronavirus to our organisation, to protect the health, safety and wellbeing of our staff and sustain our critical operations. As a result, please contact us via e-mail at psc-waterquality@environment-agency.gov.uk or contact us on 03708 506 506 to arrange to see the application documents if you do not have internet access.

How to comment on the application

If you have any comments on the application send these by 8 April 2021.

Online: view and comment on the application using Citizen Space at https://consult.environment-agency.gov.uk/psc/ta5-1ud-nnb-generation-company-hpc-limited-v008

Via email: pscpublicresponse@environment-agency.gov.uk